BLD-Aging Inspection | 8/7/2020 | 8/7/2020 | 8/7/2020 | | PEND |
Tell Riley
|
|
|
|
BLD-Final | 3/31/2020 | 4/1/2020 | 4/1/2020 | A | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Vaughn Pruett//talked with Brandon, two egress windows have not beein installed that are in the permit description//advised him to update description with Josh at plan review prior to the final for certificate of completion//he will re-schedule when complete//
|
BLD-Final | 3/26/2020 | 3/26/2020 | 3/26/2020 | P | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Vaughn Pruett up stairs ok but still needs to install windows in basement
|
BLD-Final | 3/19/2020 | 3/20/2020 | 3/20/2020 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Vaughn Pruett. Needs plumbing final.
|
BLD-Energy code compliance | 12/17/2019 | 12/18/2019 | 12/18/2019 | P | PASS |
Tell Riley
|
|
|
Call 30 minutes before. Phone #: ###-#### Inspection requested via web by Vaughn Pruett
|
BLD-Framing/Rough-in | 12/17/2019 | 12/18/2019 | 12/18/2019 | P | PASS |
Tell Riley
|
|
|
Call 30 minutes before. Phone #: ###-#### Inspection requested via web by Vaughn Pruett
|
BLD-Framing/Rough-in | 12/11/2019 | 12/12/2019 | 12/13/2019 | A | CANC |
Tell Riley
|
|
|
Please call 30 minutes before Phone #: ###-#### Inspection requested via web by Vaughn Pruett//need to provide updated truss fix to reflect onsite installation//
|
BLD-Energy code compliance | 12/11/2019 | 12/12/2019 | 12/13/2019 | A | CANC |
Tell Riley
|
|
|
Please call 30 minutes before Phone #: ###-#### Inspection requested via web by Vaughn Pruett
|
BLD-Framing/Rough-in | 12/9/2019 | 12/10/2019 | 12/10/2019 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Vaughn Pruett//add nails to girder per engineering//provide engineered truss fix for extended top and bottom chords//add studs for girder bearing per detail//ok to insulate walls only//NOTE--basement egress windows have not been installed//
|
BLD-Wall Bracing | 11/18/2019 | 11/18/2019 | 11/18/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Vaughn Pruett
|
BLD-Foundation | 10/23/2019 | 10/24/2019 | 10/24/2019 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Vaughn Pruett
|
BLD-Footing | 10/21/2019 | 10/22/2019 | 10/22/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
Issue PAID IN FULL permit | | | 10/21/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/21/2019 | | DONE |
|
|
|
|
Telephone call | | | 10/17/2019 | | DONE |
|
|
|
informed vpruett@gmail.com that we need to know who the RP will be
|
OVERRIDE | | | 10/2/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 10/2/2019 | | DONE |
|
|
|
ME
NEED
RP
|
Plan assigned to (JAB) Josh | 7/22/2019 | 7/22/2019 | 10/1/2019 | | PASS |
Josh Bogle
|
|
|
07/26 addtion, ePlan - 1st done
|
Routing - PLAN CHECK | 9/26/2019 | | 10/1/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Routing - MECHANICAL | 9/26/2019 | | 9/30/2019 | | PASS |
Troy James
|
|
|
|
Plan Reviewer's activity | | | 9/26/2019 | | DONE |
Josh Bogle
|
|
|
accepted resubmittal - routed to Mech
|
Routing - PLAN CHECK | 8/29/2019 | | 8/29/2019 | | FAIL |
Josh Bogle
|
|
|
no man J - porch bearing needs engineering - basement egress windows too small
|
Plan Reviewer's activity | | | 8/23/2019 | | DONE |
Josh Bogle
|
|
|
rejected resubmittal - plan not versioned correctly
|
Routing - PLAN CHECK | 8/22/2019 | | 8/22/2019 | | FAIL |
Josh Bogle
|
|
|
plan not versioned correctly
|
Routing - PLAN CHECK | 7/22/2019 | | 7/31/2019 | | FAIL |
Josh Bogle
|
|
|
see e-mail to Vaughn
|
1st review completed | | | 7/31/2019 | | FAIL |
Josh Bogle
|
|
|
|
Plan Reviewer's activity | | | 7/29/2019 | | DONE |
Josh Bogle
|
|
|
attempted review - plan not available in ePlan
|
Routing - PLANNING | 7/22/2019 | | 7/22/2019 | | PASS |
Jeff Lowe
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/22/2019 | | DONE |
|
|
|
no intake fee taken- 406
|
Intake Approval | | | 7/22/2019 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/19/2019 | | FAIL |
|
|
|
Drawing file names must include the first characters of the discipline name, followed by the sheet number and name. Example: A2.0_Floor Plan, the current files will need to be deleted onces the correct files names are uploaded.
|
Application received | | | 7/18/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 18 2019 5:39PM
|