BLD-Wall cover | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Will Henggeler
|
BLD-Framing/Rough-in | 6/11/2020 | 6/11/2020 | 6/11/2020 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Will Henggeler
|
Routing - MECHANICAL | 4/21/2020 | | 4/21/2020 | | PASS |
Troy James
|
|
|
resubmitted ACCA report
|
BLD-Wall Bracing | 3/25/2020 | 3/25/2020 | 3/25/2020 | P | PASS |
Dave Hannah
|
|
|
Shear Phone #: ###-#### Inspection requested via web by Will Henggeler
|
BLD-Footing | 2/28/2020 | 2/28/2020 | 2/28/2020 | P | PASS |
Dave Hannah
|
|
|
Cameron Phone #: ###-####
|
BLD-Footing | 2/26/2020 | 2/27/2020 | 2/27/2020 | A | PART |
Dave Hannah
|
|
|
concrete at 1030 // Cameron Phone #: ###-#### ftgs in slab
|
BLD-Other | 1/28/2020 | 1/28/2020 | 1/28/2020 | P | PASS |
Dave Hannah
|
|
|
steam wall // Cameron Phone #: ###-####
|
BLD-Footing | 1/21/2020 | 1/21/2020 | 1/22/2020 | P | PART |
Dave Hannah
|
|
|
Cameron Phone #: ###-####
|
BLD-Footing | 1/17/2020 | 1/17/2020 | 1/21/2020 | P | PASS |
Dave Hannah
|
|
|
Cameron Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 1/3/2020 | | DONE |
|
|
|
plan mod approved.
|
OVERRIDE | | | 1/2/2020 | | |
|
|
|
|
Plan assigned to (J_N) | 12/20/2019 | 12/20/2019 | 1/2/2020 | | DONE |
Jenny Nelson
|
|
|
plan mod
|
Routing - PLAN CHECK | 1/2/2020 | | 1/2/2020 | | PASS |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 1/2/2020 | | 1/2/2020 | | PASS |
Sue Cummings
|
|
|
Still good
|
Permit Ready to Issue | | | 1/2/2020 | | DONE |
|
|
|
DO NOT REISSUE - PLAN MOD
|
Plan Modification Accepted | | | 12/20/2019 | | DONE |
|
|
|
Christie Newkirk requested plan mod
|
BLD-Conference | 11/4/2019 | 11/4/2019 | 11/4/2019 | P | DONE |
Dave Hannah
|
|
|
review of existing floor and foundation. Phone #: ###-#### Inspection requested via web by Will Henggeler
|
Issue PAID IN FULL permit | | | 10/16/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/16/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 7/26/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 7/22/2019 | 7/22/2019 | 7/26/2019 | | DONE |
Jenny Nelson
|
|
|
08/02 sfd L1 ePlan
|
Routing - PLAN CHECK | 7/22/2019 | | 7/26/2019 | | PASS |
Jenny Nelson
|
|
|
ESC yes, Energy yes
|
1st review completed | | | 7/26/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 7/26/2019 | | DONE |
|
|
|
ALL MET- Need RP
|
Plan Reviewer's activity | | | 7/25/2019 | | DONE |
Jenny Nelson
|
|
|
Plans came in as 402, when went into to review noticed it should be 406 as basement and 3 exterior main floor walls are remaining. Had BLH help change over to correct type of permit.
|
Route to Impact Fee Review | 7/22/2019 | 7/25/2019 | 7/23/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 7/22/2019 | | 7/23/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 7/22/2019 | | 7/22/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 7/22/2019 | | 7/22/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/22/2019 | | 7/22/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/22/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/22/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/22/2019 | | DONE |
|
|
|
|
Application received | | | 7/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 19 2019 9:07AM
|
Intake Approval | | | 7/19/2019 | | FAIL |
|
|
|
Need application 402,not 406. Need RESCheck or prescriptive. Need accurate account of square footage.
|