BLD-Final | 4/14/2020 | 4/16/2020 | 4/16/2020 | P | PASS |
Brandon Shaw
|
|
|
Tempered coating going on Thursday morning Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 4/16/2020 | 4/16/2020 | 4/16/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 4/14/2020 | 4/14/2020 | 4/14/2020 | P | FAIL |
Brandon Shaw
|
|
|
Safety glazing required at stair landing window....
|
BLD-Blower Door Test Results | 4/14/2020 | 4/14/2020 | 4/14/2020 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 4.03
|
BLD-Wall Bracing | 1/13/2020 | 1/15/2020 | 1/15/2020 | A | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon//CN posted//still need to add straps and nails straps at 2nd floor--add SDS screws at shear walls//3rd floor needs 16d nails in plates at shear walls//
|
BLD-Energy code compliance | 1/13/2020 | 1/14/2020 | 1/14/2020 | P | PASS |
Brandon Shaw
|
|
|
Shear and Framing corrections SAT...
|
BLD-Framing/Rough-in | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | FAIL |
Brandon Shaw
|
|
|
See pg S3.0 for shear corrections- verify all exterior floor to floor straps are in place, as per plans... See pg S2.0 for framing corrections... See red marks on plans...
|
BLD-Framing/Rough-in | 1/9/2020 | 1/10/2020 | 1/10/2020 | P | FAIL |
Brandon Shaw
|
|
|
No city approved plans on site...
|
BLD-Wall Bracing | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | FAIL |
Brandon Shaw
|
|
|
Hold downs to be installed per manufacturers installations instructions and to be located as per plans...
|
BLD-Foundation | 9/3/2019 | 9/3/2019 | 9/3/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 8/29/2019 | 8/30/2019 | 8/30/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
OVERRIDE | | | 8/2/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 7/30/2019 | 7/30/2019 | 8/2/2019 | | DONE |
Jenny Nelson
|
|
|
08/12 sfd L1 ePlan
|
Routing - PLAN CHECK | 7/30/2019 | | 8/2/2019 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 8/2/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 8/2/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/2/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/2/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 7/30/2019 | 8/2/2019 | 7/31/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 7/30/2019 | | 7/31/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 7/30/2019 | | 7/31/2019 | | PASS |
Ethan Mansfield
|
|
|
|
Routing - Addressing | 7/30/2019 | | 7/31/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/30/2019 | | 7/30/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/30/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/30/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/30/2019 | | DONE |
|
|
|
|
Application received | | | 7/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 19 2019 9:54AM
|