BLD-Final | 10/8/2019 | 10/9/2019 | 10/9/2019 | A | PASS |
Tell Riley
|
|
|
Jessica- Phone #: ###-####//service counter is installed per plans//no other counter have been installed at this time//final complete//
|
Permanent Occupancy | | | 10/9/2019 | | DONE |
|
|
|
|
BLD-Final | 9/24/2019 | 9/25/2019 | 9/25/2019 | A | PASS |
Tell Riley
|
|
|
Jessica Phone #: ###-####//ok for temp occupancy//signed card//will issue permanant occupancy when sevice counter is completed//
|
FIRE-Final Inspection | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | PASS |
Troy Cobbley
|
|
|
life safety passed. Jessica Phone #: ###-####
|
BLD-Conference | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | DONE |
Dave Hannah
|
|
|
Jessica-after 3:00 or it will need to be rescheduled-please ccontact Jessica if you can''t make Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/9/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 7/19/2019 | 7/19/2019 | 8/8/2019 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - 518 Lark & Larder - paper
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2019 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/8/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/8/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/8/2019 | | DONE |
|
|
|
MET
Need
GC Form
Revised Value
(If appliant is acting as their own GC, we need a letter from the parcel owner allowing)
|
Telephone call | | | 8/8/2019 | | DONE |
|
|
|
Left a message for Jessica informing her permit is ready. Either need the GC fill out the 302, 306 and sign for the permit or her (tenant) to fill out the 302, 306 and letter from the parcel owner before we can put in the rest of the permit fees
|
Routing - PLUMBING | 8/2/2019 | | 8/6/2019 | | PASS |
Daryl Spivey
|
|
|
per plan and ISPC.
|
Plan resubmittals received | | | 8/2/2019 | | DONE |
|
|
|
Two copies of each P1.0 and P2.0 stamped and taken to plan reviewer
|
Route to Impact Fee Review | 7/25/2019 | 7/28/2019 | 7/26/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 7/25/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 7/23/2019 | | 7/25/2019 | | PASS |
Julie Romig
|
|
|
Building plan review passed pending Plumbing
|
Routing - PLUMBING | 7/22/2019 | | 7/23/2019 | | FAIL |
Dan Ediger
|
|
|
need engineered set of plumbing plans with pipe sizing and tie in locations to existing piping.
|
Routing - PUBLIC WORKS | 7/19/2019 | | 7/22/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Environmental | 7/22/2019 | | 7/22/2019 | | PASS |
Rick Christenson
|
|
|
Approved. No on-site meal prep.
|
Plans ACCEPTED BY PLAN TECH | | | 7/19/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/19/2019 | | PASS |
Julie Romig
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/19/2019 | | DONE |
|
|
|
|
Routing - Addressing | 7/19/2019 | | 7/19/2019 | | PASS |
Doug Chausow
|
|
|
|
Application received | | 7/19/2019 | | | |
|
|
|
|