BLD-Final | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 1/21/2020 | 1/21/2020 | 1/21/2020 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 1/17/2020 | 1/17/2020 | 1/17/2020 | A | NR |
Brandon Shaw
|
|
|
Need PW approval...
|
BLD-Blower Door Test Results | 1/17/2020 | 1/17/2020 | 1/17/2020 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.1
|
BLD-Other | 10/4/2019 | 10/4/2019 | 10/4/2019 | P | PASS |
Brandon Shaw
|
|
|
Sheetrock soffit. Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Energy code compliance | 10/1/2019 | 10/2/2019 | 10/2/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 9/30/2019 | 9/30/2019 | 10/1/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Wall Bracing | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Foundation | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 8/15/2019 | 8/15/2019 | 8/15/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 7/31/2019 | | DONE |
|
|
|
Email permits to be signed to- kdavis@boisehunterhomes.com and bhhdrafting@boisehunterhomes.com
|
Inspection Record Card- Bld | | | 7/31/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 7/30/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 7/26/2019 | 7/26/2019 | 7/30/2019 | | DONE |
Jenny Nelson
|
|
|
08/14 sfd L2 ePlan, 1st complete, waiting for ESC
|
Routing - Erosion and Sediment | 7/26/2019 | | 7/30/2019 | | PASS |
Michael Zawacki
|
|
|
Harris North foothills lot.
|
1st review completed | | | 7/30/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 7/30/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 7/26/2019 | 7/29/2019 | 7/29/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing PW Grading-Hillside | 7/26/2019 | | 7/29/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - PLAN CHECK | 7/26/2019 | | 7/29/2019 | | PASS |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 7/26/2019 | | 7/29/2019 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 7/26/2019 | 7/26/2019 | 7/26/2019 | | PASS |
Lee G Meredith
|
|
|
Sprinklers are not required.
|
Routing - Addressing | 7/26/2019 | | 7/26/2019 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/26/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/26/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/26/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 7/26/2019 | | 7/26/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - PUBLIC WORKS | 7/26/2019 | | 7/26/2019 | | PASS |
Angela Hardy
|
|
|
|
Application received | | | 7/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 24 2019 8:10AM
|