Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-02809
StatusFinaled
Name COOK BROTHERS CONSTRUCTION
Site Address 2212 N 30TH ST Unit: 110
Project NameWard ADU
Customer Number 
ePlanReviewNo
Description
(CAA19-00132, DRH19-00209) Permit to attach a 420 sq ft (21'x20') ADU to an existing detached 22'x21' Garage at the rear of the property. Mini split system proposed, Prescriptive Energy Code proposed. All work to be done as per plans, notes, and local codes. Separate electrical, plumbing and mechanical permits are required. ***BJM***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/24/20201/28/20201/28/2020PPASS
DetailsTony Young
RUSTY Phone #: ###-####
DOC - Permit Finaled1/28/20201/28/20201/28/2020PPASS
DetailsTony Young
BLD-Final1/23/20201/24/20201/24/2020PPEND
DetailsTony Young
rusty Phone #: ###-####
BLD-Final1/23/20201/23/20201/23/2020PPEND
DetailsTony Young
rusty Phone #: ###-####
BLD-Final1/22/20201/22/20201/23/2020PPEND
DetailsTony Young
Rusty Phone #: ###-####,, needs address, front and alley
Zoning Approval1/23/20201/23/20201/23/2020 DONE
DetailsKayCee Babb
Per DRH19-00209. Landscaping to remain predominately vegetative as proposed in revised plans.
BLD-Energy code compliance11/11/201911/12/201911/12/2019APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Rusty Cook
BLD-Framing/Rough-in11/7/201911/8/201911/8/2019APASS
DetailsTony Young
Rusty Phone #: ###-####
BLD-Footing9/30/20199/30/20199/30/2019PPASS
DetailsTony Young
Derek Phone #: ###-####,, ADU footing,, ok
Issue PAID IN FULL permit  9/13/2019 DONE
Route to Impact Fee Review9/4/20199/7/20199/5/2019 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
OVERRIDE  9/4/2019  
OVERRIDE  9/4/2019  
Plan assigned to (BJM)8/20/20198/20/20199/4/2019 DONE
DetailsBrian McGowan
09/03- ADU from front counter
Telephone call  9/4/2019 DONE
Left voicemail for Rusty to inform him the permit is ready, we need an RP and what fees are due.
Case Summary (BLD)  9/4/2019 DONE
DetailsBrian McGowan
Inspection Record Card- Bld  9/4/2019 DONE
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  9/4/2019 DONE
DetailsBrian McGowan
Permit Ready to Issue  9/4/2019 DONE
Need
RP
1st review completed  8/24/2019 DONE
DetailsBrian McGowan
Routing - PUBLIC WORKS8/20/2019 8/23/2019 PASS
DetailsAngela Hardy
Routing - Addressing8/20/2019 8/22/2019 PASS
DetailsDoug Chausow
Unit numbers should be displayed under address on home, ADU, and mailboxes.
Route to Impact Fee Review8/20/20198/23/20198/21/2019 PASS
DetailsShannon Cade
Routing Walk-In (Zoning)8/20/20198/20/20198/20/2019APASS
DetailsJeff Lowe
per CAA19-00132, DRH19-00209
Routing Walk-In (BLD)8/20/20198/20/20198/20/2019APASS
DetailsBrian McGowan
Plan Reviewer's activity  8/20/2019  
DetailsBrian McGowan
Took Plans to PW.
Routing - PLAN CHECK8/20/2019 8/20/2019 PASS
DetailsBrian McGowan
Routing - PLAN CHECK7/29/2019 7/29/2019 FAIL
DetailsJosh Bogle
no review - failed Planning
1st review completed  7/29/2019 FAIL
DetailsJosh Bogle
Plans ACCEPTED BY PLAN TECH  7/25/2019 DONE
Intake Approval  7/25/2019 PASS
Recd Pcfee & Taken To Pln CK  7/25/2019 DONE
Routing - PLANNING7/25/2019 7/25/2019 FAIL
DetailsKayCee Babb
ADU application/approval is required prior to submittal of Building permits. Plans match substandard lot approval.
Application received 7/25/2019