BLD-Final | 4/13/2020 | 4/13/2020 | 4/13/2020 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 4/13/2020 | 4/13/2020 | 4/13/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Blower Door Test Results | 4/13/2020 | 4/13/2020 | 4/13/2020 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon 4.7
|
BLD-Energy code compliance | 1/9/2020 | 1/9/2020 | 1/9/2020 | P | PASS |
Brandon Shaw
|
|
|
Late as possible please Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Framing/Rough-in | 1/7/2020 | 1/7/2020 | 1/7/2020 | P | PEND |
Brandon Shaw
|
|
|
Need a clean set of city approved plans and truss Engineering...
|
BLD-Framing/Rough-in | 12/30/2019 | 1/2/2020 | 1/2/2020 | P | NR |
Brandon Shaw
|
|
|
Late as possible please Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Wall Bracing | 12/13/2019 | 12/13/2019 | 12/13/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Wall Bracing | 12/10/2019 | 12/12/2019 | 12/12/2019 | A | NR |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Foundation | 9/9/2019 | 9/9/2019 | 9/9/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Foundation | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Gus Brandon Inspection cancelled from web by: Gus Brandon
|
BLD-Footing | 9/5/2019 | 9/5/2019 | 9/5/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 9/3/2019 | 9/3/2019 | 9/3/2019 | P | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Gus Brandon Inspection cancelled from web by: Gus Brandon
|
Issue PAID IN FULL permit | | | 8/22/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/22/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 8/16/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 8/2/2019 | 8/2/2019 | 8/16/2019 | | DONE |
Rob Patrick
|
|
|
08/15 sfd L1 ePlan...08/13 Failed
|
Routing - PLAN CHECK | 8/16/2019 | | 8/16/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/16/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 8/16/2019 | | DONE |
|
|
|
met
|
Meeting | | | 8/13/2019 | | DONE |
|
|
|
permit address was changed to 68/1 but should have been 58/1 with parcel # R9511771160. Address was changed from 4197 E Raincloud Ln to 4147 E Raincloud Ln. Emailed Rob P and Doug C. that i changed them
|
1st review completed | | | 8/13/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - PLANNING | 8/13/2019 | | 8/13/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLAN CHECK | 8/2/2019 | | 8/13/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Route to Impact Fee Review | 8/2/2019 | 8/5/2019 | 8/5/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 8/2/2019 | | 8/5/2019 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 8/2/2019 | | 8/5/2019 | | PASS |
Doug Chausow
|
|
|
Corrected parcel # to R9511771260
|
Routing - PUBLIC WORKS | 8/2/2019 | | 8/2/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 8/2/2019 | | 8/2/2019 | | FAIL |
Katelyn Menuge
|
|
|
Upload correct HRRB approval letter and update scale on site plan.
|
Plans ACCEPTED BY PLAN TECH | | | 8/2/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/2/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/2/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 8/2/2019 | | 8/2/2019 | | DONE |
Sue Cummings
|
|
|
I sent this to Katelyn M.
|
Application received | | | 7/26/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 26 2019 7:19AM
|