Second Notice | | 1/9/2020 | 1/23/2020 | | DONE |
|
|
|
This permit finaled on the web by Kirsten Dallmann
|
First Notice | | 12/2/2019 | 12/30/2019 | | DONE |
|
|
|
mailed 1-1-20
|
BLD-Final | 11/20/2019 | 11/22/2019 | 11/22/2019 | A | PASS |
Tony Young
|
|
|
This is for Temp Occupancy only - Inspection was done with previous permit BLD19-03142. Phone #: ###-#### Inspection requested via web by Kirsten Dallmann
MEC N/A
|
Telephone call | | | 11/22/2019 | | DONE |
|
|
|
Per phone call with Tony Y, MEC was done under vanilla permit and to mark NA on the occupancy request form.
|
Permanent Occupancy | | | 11/22/2019 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/20/2019 | 11/21/2019 | 11/21/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection for area of work complete, fire aalrm inspection for area of work is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete, signature card not availabe at time of inspection.
Later in the afternoon if possible. Please call me ahead of time so I am available, tenant is moving in furniture. This is for Temp Occupancy only - Inspection was done with previous permit BLD19-03142. Phone #: ###-#### Inspection requested via web by Kirsten Dallmann
|
Issue PAID IN FULL permit | | | 11/20/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/20/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 7/29/2019 | 7/31/2019 | 11/19/2019 | | DONE |
Julie Romig
|
|
|
11/20 - 3rd Rev - 1st Rev Comp - L3 Hall Academy (Expedited)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/19/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/19/2019 | | DONE |
|
|
|
(kirsten@sawtoothdevelopment.com)
ALL MET
Need
Revised Cert of Value
GC Form
|
Routing - PLANNING | 8/19/2019 | | 11/19/2019 | | FAIL |
Stephanie Leonard
|
|
|
Corrections required per ePlanReview
|
Routing - PLANNING | 11/14/2019 | | 11/19/2019 | | PASS |
Celine Acord
|
|
|
Passed per ePlanReview and Celine Accord.
|
Routing - PLAN CHECK | 11/14/2019 | | 11/14/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - FIRE | 8/19/2019 | 8/19/2019 | 8/26/2019 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case
|
Meeting | | | 8/19/2019 | | DONE |
|
|
|
Per Julie this permit will only for for occupancy so the value is only 501
|
Routing - PLAN CHECK | 8/19/2019 | | 8/19/2019 | | FAIL |
Julie Romig
|
|
|
Permit cannot be issued without approved CUP. All other Building plan review items have passed.
|
Route to Impact Fee Review | 8/9/2019 | 8/12/2019 | 8/12/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 7/31/2019 | 7/31/2019 | 8/9/2019 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
1st review completed | | | 8/9/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 7/31/2019 | | 8/9/2019 | | FAIL |
Julie Romig
|
|
|
Refer to IBC Plan Review Report for corrections. Building permit cannot be issued until CUP is approved.
|
Routing - PLANNING | 7/31/2019 | | 8/9/2019 | | FAIL |
Stephanie Leonard
|
|
|
Need CUP to establish education use - P&Z hearing scheduled for 9/9/2019
|
Routing - Addressing | 7/31/2019 | | 7/31/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/31/2019 | | 7/31/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 7/29/2019 | | |
|
|
|
|
Application received | | | 7/28/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 28 2019 4:23PM
|