Permit Information
Permit NumberBLD19-02888
StatusFinaled
Name TV GROUP LLC
Site Address 10371 W UTAHNA RD
Project NameYoung
Customer Number 
ePlanReviewYes
Description
Permit to excavate and pour foundation/footings, along with landings, stairs, handrails and guard rails, as required for a 1386 sq. ft. double wide manufactured home. Idaho State Insignia No. on the home is FLE230ID1934537AB. All work per plans, manufacturers documentation and local codes. Separate Mechancial, Electrical and Plumbing permits are required. ***RDP***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/22/201911/25/201911/25/2019APASS
DetailsTony Young
KITTY Phone #: ###-####
DOC - Permit Finaled11/25/201911/25/201911/25/2019PPASS
DetailsTony Young
DOC - Permit Finaled11/25/201911/25/201911/25/2019PPASS
DetailsTony Young
Letter of compliance/Occupancy  11/25/2019 DONE
BLD-Final11/21/201911/22/201911/22/2019AFAIL
DetailsMike Jordan
Katie Phone #: ###-####. Needs to post address. eceryhing else ok. Correction noitce posted.
BLD-Foundation9/20/20199/23/20199/23/2019APASS
DetailsTell Riley
Mud at 11 - Tiffany-stem wall Phone #: ###-####
BLD-Footing9/16/20199/16/20199/16/2019PPASS
DetailsTell Riley
ok per approved plans
BLD-Foundation9/13/20199/16/20199/16/2019PCANC
DetailsTell Riley
Tiffany Phone #: ###-####
Issue PAID IN FULL permit  9/6/2019 DONE
Inspection Record Card- Bld  9/6/2019 DONE
Telephone call  8/29/2019 DONE
Called and left a VM informing contractor that we need an RP
Plan assigned to (RDP)8/6/20198/6/20198/23/2019 DONE
DetailsRob Patrick
08/23 sfd L2 ePlan...08/21 Failed
Routing - PLANNING8/23/2019 8/23/2019 PASS
DetailsSue Cummings
Site plan O.K. now...not sure what the project map is.
Routing - PLAN CHECK8/23/2019 8/23/2019 PASS
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  8/23/2019 DONE
DetailsRob Patrick
Permit Ready to Issue  8/23/2019 DONE
MET
Need
RP
1st review completed  8/21/2019 FAIL
DetailsRob Patrick
Routing - PLAN CHECK8/6/2019 8/21/2019 FAIL
DetailsRob Patrick
Corrections Required
Routing - Addressing8/6/2019 8/8/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS8/6/2019 8/7/2019 PASS
DetailsMorgan Webb
Routing - PLANNING8/6/2019 8/7/2019 FAIL
DetailsSue Cummings
Needs compliant parking. Asphalt 40 ft. deep 18 ft. wide.
Intake Approval  8/6/2019 FAIL
2nd pre screen 8-6-19: please rotate plan sheets to the correct orientation (landscape)
Plans ACCEPTED BY PLAN TECH  8/6/2019 DONE
Intake Approval  8/6/2019 PASS
Recd Pcfee & Taken To Pln CK  8/6/2019 DONE
Route to Impact Fee Review7/30/20198/2/20197/31/2019 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
Application received  7/30/2019 DONE
Application submitted via PDS Online on Jul 30 2019 11:41AM
Intake Approval  7/30/2019 FAIL
as per our conversation-we need the drawings in the drawings folder-they need to face landscape way, uploaded individually-need site plan with setbacks on it-
drawings need to be detailed enough that someone could go out and build what you have on the drawings, also that way the plan reviewer will be able to do his plan review and make sure it all meets code