First Notice | | 5/31/2020 | 7/9/2020 | | DONE |
|
|
|
mailed 7-9-2020
|
Permanent Occupancy | | | 5/21/2020 | | DONE |
|
|
|
|
BLD-Final | 5/14/2020 | 5/15/2020 | 5/15/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2085591460 >> Inspection requested via mobile web by Aaron Carroll. Ok for perm occ.
|
Temporary Occupancy | 5/8/2020 | 8/6/2020 | 5/8/2020 | | DONE |
Gabe Brenner
|
|
|
|
BLD-Final | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PART |
Mike Jordan
|
|
|
Call for access Phone #: 2085591460 >> Inspection requested via mobile web by Aaron Carroll. Ok for temp. occ. Noted vertical grab bars not within the 39 to 41 inch.
|
FIRE-Final Inspection | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Phone #: 2085591460 >> Inspection requested via mobile web by Aaron Carroll
|
FIRE-Final Inspection | 4/30/2020 | 4/30/2020 | 4/30/2020 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
Phone #: 2085591460 >> Inspection requested via mobile web by Aaron Carroll
|
FIRE-Final Inspection | 4/28/2020 | 4/29/2020 | 4/29/2020 | P | FAIL |
Troy Cobbley
|
|
|
Still need the emergency lights repaired for a life safety final.
Screened-ARMANDO Phone #: ###-####
|
Zoning Approval | 4/29/2020 | 4/29/2020 | 4/29/2020 | | PASS |
Josh Wilson
|
|
|
|
FIRE-Final Inspection | 4/27/2020 | 4/28/2020 | 4/28/2020 | A | FAIL |
Troy Cobbley
|
|
|
Provide small documents, provide address as discussed, repair emergency lights as marked on the city approved plans.
*screened* Armando Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | PASS |
Mike Jordan
|
|
|
*screened* Amando Phone #: ###-####
|
BLD-Energy code compliance | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | PASS |
Mike Jordan
|
|
|
Armando Phone #: ###-####
|
BLD-Framing/Rough-in | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | PASS |
Mike Jordan
|
|
|
armando Phone #: ###-####. Interior steel stud framed walls ok.
|
CHANGE STATUS TO (ISS) | | | 2/11/2020 | | DONE |
|
|
|
PLAN MOD APPROVED- DO NO RE ISSUE
|
BLD-Other | 2/6/2020 | 2/6/2020 | 2/6/2020 | P | DEFR |
Mike Jordan
|
|
|
roof before cover // Armando Phone #: ###-####. Ok to cover pending special inspection.
|
OVERRIDE | | | 2/5/2020 | | |
|
|
|
|
Plan assigned to (JG) | 1/21/2020 | 1/21/2020 | 2/5/2020 | | PASS |
Javier Guzman
|
|
|
01/30 Plan Mod Intrastar ePlan
|
Telephone call | | | 2/5/2020 | | DONE |
|
|
|
no building plan reviewer fee for the plan mod that was submitted on 1/21/20 per Carl Madsen
|
Permit Ready to Issue | | | 2/5/2020 | | DONE |
|
|
|
DO NOT RE ISSUE- plan mod approved
|
Routing - FIRE | 1/23/2020 | 1/23/2020 | 2/4/2020 | | PASS |
Mark Stumbaugh
|
|
|
01/30 Plan Mod Intrastar ePlan
|
Routing - PLAN CHECK | 1/23/2020 | | 2/3/2020 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 1/23/2020 | | 1/27/2020 | | PASS |
Troy James
|
|
|
Added screen printing tool
|
BLD-Framing/Rough-in | 1/22/2020 | 1/23/2020 | 1/23/2020 | A | PASS |
Mike Jordan
|
|
|
Armando Phone #: ###-####. Exterior sheathing ok. Verified sheeting is fire treated.
|
Plan Modification Accepted | | | 1/21/2020 | | DONE |
|
|
|
Modifications to equipment plan including new mechanical and electrical work.
|
BLD-Framing/Rough-in | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | PASS |
Mike Jordan
|
|
|
armando Phone #: ###-####. Exterior steel stud walls and roof for compressor room ok to shaeet.
|
BLD-Other | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PART |
Mike Jordan
|
|
|
Armando- massory inspection Phone #: ###-####. Work in progress on south east corner of masonry wall at 8ft. to 12ft. elevation. Ok for grout pending special inspection.
|
BLD-Concrete | 12/13/2019 | 12/16/2019 | 12/16/2019 | A | DEFR |
Mike Jordan
|
|
|
Aramado- pouring concrete please as early as possible Phone #: ###-####. Work in progress. Ok to grout pending special inspection.
|
BLD-Foundation | 11/27/2019 | 12/3/2019 | 12/3/2019 | P | PASS |
Mike Jordan
|
|
|
rebar // Armando Phone #: ###-####. Interior slab on grade.
|
BLD-Footing | 11/18/2019 | 11/19/2019 | 11/19/2019 | A | PART |
Mike Jordan
|
|
|
Armando Phone #: ###-####. West stemwall, work in progress. Ok to place concrete pending special inspection.
|
BLD-Foundation | 11/14/2019 | 11/15/2019 | 11/18/2019 | A | PASS |
Dave Hannah
|
|
|
rebar // armondo Phone #: ###-####
|
BLD-Foundation | 11/6/2019 | 11/8/2019 | 11/8/2019 | P | PEND |
Dave Hannah
|
|
|
rebar // Armando Phone #: ###-#### this is a ftg inspection looks good but not done spec inspection will sign off monday befor placement
|
OVERRIDE | | | 10/23/2019 | | |
|
|
|
|
Route to Impact Fee Review | 10/22/2019 | 10/25/2019 | 10/23/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JG) | 8/13/2019 | 8/16/2019 | 10/23/2019 | | PASS |
Javier Guzman
|
|
|
10/23 3rev, 09/23 - 502 Intrastar (71 pages)
|
Routing - Erosion and Sediment | 10/23/2019 | | 10/23/2019 | | PASS |
Andy J. Long
|
|
|
VOID. See ESC permit issued with GRD permit, ESC19-01049
|
Issue PAID IN FULL permit | | | 10/23/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/23/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/23/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/22/2019 | | 10/23/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/23/2019 | | DONE |
|
|
|
**let applicant know that he needs to email Tisha a request for refund for ESC19-01055
ALL MET-
Need GC
Need Rev Val
met: Need RP see ESC19-01049
|
Routing - Design Review | 10/22/2019 | | 10/22/2019 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLAN CHECK | 10/8/2019 | | 10/15/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 10/8/2019 | | 10/15/2019 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by KPFF engineer
|
Routing - Design Review | 10/8/2019 | | 10/11/2019 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLANNING | 10/8/2019 | | 10/10/2019 | | PASS |
David Moser
|
|
|
|
Routing PW Sewer Design | 10/8/2019 | | 10/8/2019 | | PASS |
DeAnn Brown
|
|
|
|
1st review completed | | | 9/30/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 8/16/2019 | | 9/30/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 8/13/2019 | 8/16/2019 | 9/23/2019 | | PASS |
Mark Stumbaugh
|
|
|
09/23 - 502 Intrastar
|
Routing PW Street Lights | 8/16/2019 | | 9/20/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 8/16/2019 | | 9/20/2019 | | FAIL |
DeAnn Brown
|
|
|
Label existing sewer manholes with City of Boise manhole numbers. Note on existing service that is not to be used currently, to protect and retain for future use.
|
Routing PW Solid Waste | 8/16/2019 | | 9/20/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Environmental | 8/16/2019 | | 9/20/2019 | | PASS |
Rick Christenson
|
|
|
On-Site BMP's for screen washout area
|
Routing Off Site - STRUCTURAL | 8/16/2019 | | 9/19/2019 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by KPFF engineer
|
Routing PW Drainage | 8/16/2019 | | 9/19/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - MECHANICAL | 8/16/2019 | | 8/22/2019 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 8/20/2019 | | 8/20/2019 | | PASS |
Michael Zawacki
|
|
|
RP needed.
Site prep inspection required after all BMPs installed and before any ground disturbing construction activities.
|
Routing - Addressing | 8/16/2019 | | 8/20/2019 | | PASS |
Laura Hunter
|
|
|
|
Routing - Design Review | 8/16/2019 | | 8/19/2019 | | FAIL |
Andrea Tuning
|
|
|
Obtain a Conditional Use Permit.
Provide a minimum of 37-parking stalls with a maximum of 14 of the spaces allowed to be compact or obtain a parking reduction that is reviewed and approved by the Boise City Planning and Zoning Commission.
Install 7 Class II or Class III trees along the west property line adjacent to the site’s drive aisle.
|
Routing - PLUMBING | 8/16/2019 | | 8/19/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC
|
Routing - PLANNING | 8/16/2019 | | 8/16/2019 | | FAIL |
David Moser
|
|
|
need to ait for CUP approval (CUP19-00043)
|
Routing - PUBLIC WORKS | 8/16/2019 | | 8/16/2019 | | PASS |
Morgan Webb
|
|
|
|
Plan Reviewer's activity | | | 8/13/2019 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 8/13/2019 | | PASS |
Carl Westfall
|
|
|
|
Intake Approval | | | 8/6/2019 | | FAIL |
|
|
|
(8-6-19) Refer to the circled items in the Plan Intake Checklist. Resolve each item as directed. If you have a question, contact Carl J. Westfall at ###-####.
|
Intake Approval | | | 8/6/2019 | | FAIL |
|
|
|
(8-6-19) Upload the Conditional Use Approval. CJW
|
Application received | | | 8/2/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 2 2019 10:46AM
|