Permit NumberBLD19-02987
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 2394 S TRAPPER PL
Project NameLot 28 Block 1 Harris North
Customer Number 
ePlanReviewYes
Description
***W.U.I. FOOTHILLS LOT ZONE A; CLASS "A" ROOF AND NON-COMBUSTIBLE EXTERIOR MATERIALS REQUIRED*** Permit for the construction of a new 3347 sq. ft., two story (first story 2153 sq. ft., second story 1194 sq. ft.) single family dwelling with 5 bedrooms, 4 bathrooms, approximately 326 sq. ft. of covered patio/porch and a 924 sq. ft. attached garage per the approved plans and any notations. SP-01 zoning and setbacks per planning. ***SPRINKLERS ARE NOT REQUIRED***LGM A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/4/20203/5/20203/5/2020APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
DOC - Permit Finaled3/5/20203/5/20203/5/2020PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results3/5/20203/5/20203/5/2020ADONE
DetailsBrandon Shaw
ACH50- 379
BLD-Final2/28/20203/2/20203/2/2020ANR
DetailsBrandon Shaw
Need trades...
PubWorks Occupancy Approval1/24/20201/24/20201/24/2020 DONE
DetailsMelissa Jannusch
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.

BLD-Energy code compliance12/17/201912/17/201912/17/2019PPASS
DetailsBrandon Shaw
BLD-Framing/Rough-in12/17/201912/17/201912/17/2019PPASS
DetailsBrandon Shaw
Corrections SAT...
BLD-Framing/Rough-in12/10/201912/11/201912/11/2019APASS
DetailsBrandon Shaw
Les Phone #: ###-####
BLD-Other12/6/201912/6/201912/6/2019PPASS
DetailsBrandon Shaw
soffit // Les Phone #: ###-####
BLD-Wall Bracing11/4/201911/4/201911/4/2019PPASS
DetailsBrandon Shaw
Les Phone #: ###-####
BLD-Foundation9/19/20199/19/20199/19/2019PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing9/18/20199/18/20199/18/2019ANR
DetailsBrandon Shaw
Need soil subgrade submitted and approved by PW...
PubWorks Subgrade Approval9/18/20199/18/20199/18/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

BLD-Footing9/15/20199/16/20199/16/2019PCANC
DetailsBrandon Shaw
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
Issue PAID IN FULL permit  9/4/2019 DONE
Inspection Record Card- Bld  9/4/2019 DONE
OVERRIDE  9/3/2019  
Plan assigned to (RDP)8/16/20198/16/20199/3/2019 DONE
DetailsRob Patrick
09/04 sfd L2 eplan
Routing - PLAN CHECK8/16/2019 9/3/2019 PASS
DetailsRob Patrick
1st review completed  9/3/2019 DONE
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  9/3/2019 DONE
DetailsRob Patrick
Permit Ready to Issue  9/3/2019 DONE
Routing PW Grading-Hillside8/16/2019 8/26/2019 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Routing - Addressing8/16/2019 8/20/2019 PASS
DetailsLaura Hunter
Route to Impact Fee Review8/16/20198/19/20198/19/2019 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - FIRE8/16/20198/16/20198/19/2019 PASS
DetailsLee G Meredith
08/29-2394 S Trapper Pl. RES ePlan LGM

Sprinklers are not required.
Routing - MECHANICAL8/16/2019 8/19/2019 PASS
DetailsTroy James
Routing - PLANNING8/16/2019 8/16/2019 PASS
DetailsSue Cummings
Plans ACCEPTED BY PLAN TECH  8/16/2019 DONE
Intake Approval  8/16/2019 PASS
Recd Pcfee & Taken To Pln CK  8/16/2019 DONE
Routing - PUBLIC WORKS8/16/2019 8/16/2019 PASS
DetailsAngela Hardy
Routing - Erosion and Sediment8/16/2019 8/16/2019 PASS
DetailsMichael Zawacki
Harris North, foothills home.
Intake Approval  8/9/2019 FAIL
Please provide original building permit number the existing retaining wall was approved with prior to acceptance of the permit for building permit review. -MMJ ###-####
Application received  8/6/2019 DONE
Application submitted via PDS Online on Aug 6 2019 10:55AM