BLD-Final | 8/12/2020 | 8/12/2020 | 8/12/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
DOC - Permit Finaled | 8/12/2020 | 8/12/2020 | 8/12/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 8/12/2020 | 8/12/2020 | 8/12/2020 | P | DONE |
Brandon Shaw
|
|
|
ACH50 -5.8
|
Routing - MECHANICAL | 6/9/2020 | | 6/9/2020 | | PASS |
Troy James
|
|
|
Resubmitted manual j report to add shop in garage
|
BLD-Energy code compliance | 6/8/2020 | 6/8/2020 | 6/8/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
OVERRIDE | | | 6/5/2020 | | |
|
|
|
|
Plan assigned to (J_N) | 5/29/2020 | 5/29/2020 | 6/5/2020 | | DONE |
Jenny Nelson
|
|
|
06/04 res plan mod
|
Routing - PLANNING | 5/29/2020 | | 6/5/2020 | | PASS |
Sue Cummings
|
|
|
Plan Mod to add square footage - stoarge space off garage
|
CHANGE STATUS TO (ISS) | | | 6/5/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/5/2020 | | 6/5/2020 | | PASS |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 6/5/2020 | | DONE |
|
|
|
plan mod approved
|
Routing PW Flood Plain | 5/29/2020 | | 6/2/2020 | | PASS |
Jason C. Taylor
|
|
|
Approved LOMR (LOMR 19-10-0196P )on File. No floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
BLD-Framing/Rough-in | 5/29/2020 | 5/29/2020 | 5/29/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
Plan Modification Accepted | | | 5/29/2020 | | DONE |
|
|
|
Adding in Garage adding 10x52 storage.
|
Routing - PUBLIC WORKS | 5/29/2020 | | 5/29/2020 | | PASS |
Candy A. Nichols
|
|
|
Plan Mod to add square footage - stoarge space off garage - Not sure if Flood Plain needs to see again.
|
BLD-Wall Bracing | 4/22/2020 | 4/22/2020 | 4/22/2020 | P | PASS |
Brandon Shaw
|
|
|
Rudy **Cleared** a Phone #: ###-####
|
Elevation Cert Rec'd-Midconst | | | 11/1/2019 | | DONE |
|
|
|
recieved EC #2, Ok to frame. JCT
|
BLD-Foundation | 9/26/2019 | 9/26/2019 | 9/26/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 9/25/2019 | 9/25/2019 | 9/25/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
Inspection Record Card- Bld | | | 9/17/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/16/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 8/22/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 8/7/2019 | 8/7/2019 | 8/22/2019 | | DONE |
Jenny Nelson
|
|
|
08/26 sfd L2 ePlan. 1st complete 08/14, wall bracing inadequate
|
Routing - PLAN CHECK | 8/22/2019 | | 8/22/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 8/22/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/15/2019 | | 8/15/2019 | | FAIL |
Jenny Nelson
|
|
|
no corrections
|
Routing - PLANNING | 8/15/2019 | | 8/15/2019 | | PASS |
Sue Cummings
|
|
|
Letter from HRRB included now
|
1st review completed | | | 8/14/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 8/7/2019 | | 8/14/2019 | | FAIL |
Jenny Nelson
|
|
|
Wall bracing
|
Routing PW Flood Plain | 8/7/2019 | | 8/14/2019 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor ###-####
|
Route to Impact Fee Review | 8/7/2019 | 8/10/2019 | 8/8/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 8/7/2019 | | 8/8/2019 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 8/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 7 2019 8:43AM
|
Telephone call | | | 8/7/2019 | | DONE |
|
|
|
Amy called to inform us that the wrong document was uploaded and asked if we could send the upload task back to her.
|
Plans ACCEPTED BY PLAN TECH | | | 8/7/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/7/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/7/2019 | | PASS |
|
|
|
|
Routing - MECHANICAL | 8/7/2019 | | 8/7/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/7/2019 | | 8/7/2019 | | FAIL |
Sue Cummings
|
|
|
Approval letter from Harris Ranch Review Board is required. Thanks!
|
Routing - PUBLIC WORKS | 8/7/2019 | | 8/7/2019 | | PASS |
Morgan Webb
|
|
|
|