BLD-Final | 7/9/2020 | 7/9/2020 | 7/9/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
DOC - Permit Finaled | 7/9/2020 | 7/9/2020 | 7/9/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 7/9/2020 | 7/9/2020 | 7/9/2020 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 4.4
|
BLD-Energy code compliance | 4/30/2020 | 5/1/2020 | 5/1/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
BLD-Framing/Rough-in | 4/27/2020 | 4/28/2020 | 4/28/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
BLD-Wall Bracing | 4/7/2020 | 4/7/2020 | 4/7/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
BLD-Energy code compliance | 4/6/2020 | 4/7/2020 | 4/7/2020 | P | CANC |
Brandon Shaw
|
|
|
no one will be onsite // rudy Phone #: ###-#### Inspection cancelled from web by: Laz Ponce
|
BLD-Framing/Rough-in | 3/23/2020 | 3/24/2020 | 3/24/2020 | A | FAIL |
Jim Storey
|
|
|
Rudy Phone #: ###-#### need pw flood plain cert signed off
|
BLD-Wall Bracing | 3/19/2020 | 3/20/2020 | 3/20/2020 | A | NR |
Jim Storey
|
|
|
Rudy Phone #: ###-#### need pw flood plain cert signed off .
|
BLD-Foundation | 10/3/2019 | 10/4/2019 | 10/4/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
(F) Reprint permit | | | 9/25/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/25/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/23/2019 | | DONE |
|
|
|
emailed Amy Nutall to sign permits and send back
|
Inspection Record Card- Bld | | | 9/23/2019 | | DONE |
|
|
|
put in e plan
|
OVERRIDE | | | 8/22/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 8/16/2019 | 8/16/2019 | 8/22/2019 | | DONE |
Jenny Nelson
|
|
|
09/03 sfd L2 ePlan. 1st complete 08/20, failed planning.
|
Routing - PLANNING | 8/22/2019 | | 8/22/2019 | | PASS |
Sue Cummings
|
|
|
HRRB letter provided 8/22/19.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 8/22/2019 | | DONE |
|
|
|
met
|
1st review completed | | | 8/21/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing PW Flood Plain | 8/16/2019 | | 8/21/2019 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor ###-####
|
Elevation Cert Rec'd-Prelim | | | 8/21/2019 | | DONE |
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor ###-####
|
Routing - Addressing | 8/16/2019 | | 8/20/2019 | | PASS |
Laura Hunter
|
|
|
|
Routing - PLAN CHECK | 8/16/2019 | | 8/20/2019 | | PASS |
Jenny Nelson
|
|
|
|
Route to Impact Fee Review | 8/16/2019 | 8/19/2019 | 8/19/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 8/16/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/16/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/16/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 8/16/2019 | | 8/16/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/16/2019 | | 8/16/2019 | | FAIL |
Sue Cummings
|
|
|
Please provide the HRRB approval letter.
|
Routing - PUBLIC WORKS | 8/16/2019 | | 8/16/2019 | | PASS |
Angela Hardy
|
|
|
|
Application received | | | 8/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 7 2019 8:53AM
|
Intake Approval | | | 8/7/2019 | | FAIL |
|
|
|
Manual J and ResCheck both have 310 S Millbrook as the address instead of 3100. Please have the addresses corrected and re-upload them.
|