BLD-Final | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
DOC - Permit Finaled | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Mike Jordan
|
|
|
All issues were resolved.
|
BLD-Blower Door Test Results | 3/3/2020 | 3/3/2020 | 3/3/2020 | A | DONE |
Mike Jordan
|
|
|
5.5
|
BLD-Final | 2/27/2020 | 2/28/2020 | 2/28/2020 | A | NR |
Tell Riley
|
|
|
Jeff Phone #: ###-####//fill out insulation cert//need blower door test//CN posted//
|
BLD-Energy code compliance | 12/16/2019 | 12/16/2019 | 12/16/2019 | P | PASS |
Tell Riley
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/16/2019 | 12/16/2019 | 12/16/2019 | P | PASS |
Tell Riley
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/11/2019 | 12/12/2019 | 12/12/2019 | A | PART |
Tell Riley
|
|
|
Jeff Phone #: ###-####//correction notice issued//add bearing header over entry door for mono truss bearing//ok to insulate only//
|
BLD-Wall Bracing | 11/13/2019 | 11/13/2019 | 11/13/2019 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Wall Bracing | 11/12/2019 | 11/12/2019 | 11/12/2019 | P | FAIL |
Tell Riley
|
|
|
Jeff Phone #: ###-####//add approved fasteners to sill plate around building//add nails per detail to blocking and sill plate at portal frame//correction notice posted//
|
BLD-Footing | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PART |
Tell Riley
|
|
|
James Phone #: ###-####//setbacks ok//house was flipped on lot//will need plan mod for approval of flip//pour at builders own risk//rebar installed per plans//
|
Issue PAID IN FULL permit | | | 8/30/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/30/2019 | | DONE |
|
|
|
|
Telephone call | | | 8/30/2019 | | DONE |
|
|
|
ALL MET-EMAILED permit to be signed to jwmilich@msn.com release EPLAN
|
OVERRIDE | | | 8/29/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 8/29/2019 | | DONE |
|
|
|
|
Plan assigned to (RDP) | 8/14/2019 | 8/14/2019 | 8/28/2019 | | DONE |
Rob Patrick
|
|
|
08/28 sfd L1 ePlan
|
Routing - PLAN CHECK | 8/14/2019 | | 8/28/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 8/28/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/28/2019 | | DONE |
Rob Patrick
|
|
|
|
Routing - MECHANICAL | 8/14/2019 | | 8/16/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 8/14/2019 | 8/17/2019 | 8/15/2019 | | PASS |
Shannon Cade
|
|
|
Can not find the parcel in the GIS system, the building permit may have been assigned a temporary parcel number
|
Routing - PLANNING | 8/14/2019 | | 8/14/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 8/14/2019 | | 8/14/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/14/2019 | | 8/14/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/14/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/14/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/14/2019 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/8/2019 | | FAIL |
|
|
|
Electrical Plan needed to show bathroom exhaust fan, cfm, smoke alarms and carbon monoxide alarm locations.
|
Application received | | | 8/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 7 2019 9:58AM
|