Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-03027
StatusFinaled
Name DIRTMAN LLC
Site Address 3620 S DURHAM WAY
Project NameLECHT RESIDENCE
Customer NumberDEMO BLD19-02402
ePlanReviewNo
Description
Permit for a new foundation for a new manufactured home. Previous home demo BLD19-02402. All work per plans, manufacturer's specs, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance/Occupancy  6/25/2020 DONE
BLD-Final9/23/20199/24/20199/24/2019APASS
DetailsBrandon Shaw
Keith Phone #: ###-####
DOC - Permit Finaled9/24/20199/24/20199/24/2019PPASS
DetailsBrandon Shaw
CHANGE STATUS TO (ISS)  9/20/2019 DONE
changed status to iss. Customer came in for a question on about his plans. Had no plans with him so it was marked as fialed. no changes were made.
Routing Walk-In (BLD)9/12/20199/12/20199/12/2019AFAIL
DetailsBrian McGowan
Had no drawings or documents
Routing - PLAN CHECK9/12/2019 9/12/2019 FAIL
DetailsBrian McGowan
Had no drawings or documents
BLD-Foundation9/5/20199/5/20199/5/2019PPASS
DetailsBrandon Shaw
wall // Keith Phone #: ###-####
BLD-Footing9/3/20199/3/20199/3/2019PPASS
DetailsBrandon Shaw
Work in progress...
OVERRIDE  8/19/2019  
Plan assigned to (JAB) Josh8/8/20198/8/20198/19/2019 PASS
DetailsJosh Bogle
08/14 man home, paper - 1st done
Issue PAID IN FULL permit  8/19/2019 DONE
Telephone call  8/19/2019 DONE
left message for contractor letting him know the permit is ready and what fees are due.
Routing - PLANNING8/19/2019 8/19/2019 PASS
DetailsSue Cummings
See redlines on site plan.
Routing - PLAN CHECK8/19/2019 8/19/2019 PASS
DetailsJosh Bogle
Inspection Record Card- Bld  8/19/2019 DONE
DetailsJosh Bogle
Case Summary (BLD)  8/19/2019 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  8/19/2019 DONE
DetailsJosh Bogle
ESC yes - Energy no
Permit Ready to Issue  8/19/2019 DONE
met
NEED
RP
Routing - PLAN CHECK  8/14/2019 FAIL
DetailsJosh Bogle
Routing - PLANNING8/12/2019 8/14/2019 FAIL
DetailsSue Cummings
Needs to show where compliant park will be located, which needs to be paved.
1st review completed  8/14/2019 FAIL
DetailsJosh Bogle
Routing - PUBLIC WORKS8/8/2019 8/12/2019 PASS
DetailsMorgan Webb
Route to Impact Fee Review8/8/20198/11/20198/9/2019 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - Addressing  8/9/2019 PASS
Routing Walk-In (BLD)8/8/20198/8/20198/8/2019AFAIL
DetailsJosh Bogle
question on submitting plans for manufactured home
Plans ACCEPTED BY PLAN TECH  8/8/2019 DONE
Recd Pcfee & Taken To Pln CK  8/8/2019 DONE
NO INTAKE FEES TAKEN
Intake Approval  8/8/2019 PASS
Application received 8/8/2019