BLD-Final | 1/3/2020 | 1/3/2020 | 1/3/2020 | P | PASS |
Mike Jordan
|
|
|
Garage code 7530 Phone #: ###-#### Inspection requested via web by Rustin Ray
|
BLD-Blower Door Test Results | 1/3/2020 | 1/3/2020 | 1/3/2020 | A | DONE |
Mike Jordan
|
|
|
5.7
|
DOC - Permit Finaled | 1/3/2020 | 1/3/2020 | 1/3/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 11/5/2019 | 11/6/2019 | 11/6/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Rustin Ray
|
BLD-Framing/Rough-in | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Rustin Ray
|
BLD-Wall Bracing | 10/17/2019 | 10/18/2019 | 10/18/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Rustin Ray
|
BLD-Foundation | 9/16/2019 | 9/16/2019 | 9/16/2019 | A | PASS |
Mike Jordan
|
|
|
ready for inspection Phone #: ###-#### Inspection requested via web by Jay Jones
|
BLD-Footing | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Rustin Ray//ok per approved plans//
|
BLD-Footing | 9/10/2019 | 9/11/2019 | 9/11/2019 | A | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Rustin Ray///need city approved plans onsite//front property line need to be properly marked//
|
Fees Due Hold | 9/10/2019 | 9/10/2019 | 9/10/2019 | | DONE |
|
|
|
per Mike Jordan for reinspection fee
|
BLD-Footing | 9/10/2019 | 9/10/2019 | 9/10/2019 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Rustin Ray. Footting depth does not meet the minimum 8 inch depth in several areas.
|
BLD-Footing | 9/9/2019 | 9/10/2019 | 9/10/2019 | A | FAIL |
Mike Jordan
|
|
|
Can we schedule this for around 11:00 Phone #: ###-#### Inspection requested via web by Rustin Ray. No city approve d plans on site.
|
Issue PAID IN FULL permit | | | 9/4/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/4/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/3/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 8/8/2019 | 8/8/2019 | 9/3/2019 | | DONE |
Rob Patrick
|
|
|
08/21 sfd L1 ePlan...08/19 Failed du to Fire review
|
Routing - PLAN CHECK | 9/3/2019 | | 9/3/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/3/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 9/3/2019 | | DONE |
|
|
|
met NEED RP
|
Plan Reviewer's activity | | | 8/29/2019 | | |
|
|
|
Emailed Lee that his comment wasn't addressed. Re-submittal due 09-03.
|
Routing - FIRE | 8/16/2019 | 8/16/2019 | 8/19/2019 | | PASS |
Lee G Meredith
|
|
|
08/29-Graywoods 15-1 ePlan 402
Driveway exceeds maximum length and minimum width. Resubmittal required.
9-3-19. Received a release from Stetson Homes that releases the fire department from liability to driveway damage.
|
1st review completed | | | 8/19/2019 | | FAIL |
Rob Patrick
|
|
|
Failed due to Fire Review
|
Routing - PLAN CHECK | 8/8/2019 | | 8/19/2019 | | FAIL |
Rob Patrick
|
|
|
|
Routing - MECHANICAL | 8/8/2019 | | 8/12/2019 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 8/8/2019 | | 8/12/2019 | | PASS |
Doug Chausow
|
|
|
|
Route to Impact Fee Review | 8/8/2019 | 8/11/2019 | 8/9/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PUBLIC WORKS | 8/8/2019 | | 8/9/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 8/8/2019 | | 8/9/2019 | | PASS |
Jeff Lowe
|
|
|
|
Application received | | | 8/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 8 2019 10:35AM
|
Plans ACCEPTED BY PLAN TECH | | | 8/8/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/8/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/8/2019 | | DONE |
|
|
|
|