BLD-Wall Bracing | 3/19/2020 | 3/20/2020 | 3/26/2020 | A | PEND |
Dave Hannah
|
|
|
shear // charlie Phone #: ###-####
|
BLD-Framing/Rough-in | 3/11/2020 | 3/11/2020 | 3/12/2020 | P | PART |
Dave Hannah
|
|
|
Charlie Phone #: ###-#### hard lids ok to cover
|
BLD-Framing/Rough-in | 3/9/2020 | 3/9/2020 | 3/9/2020 | P | PASS |
Brandon Shaw
|
|
|
Raised dining area floor...
|
BLD-Framing/Rough-in | 2/27/2020 | 2/28/2020 | 3/3/2020 | P | PART |
Dave Hannah
|
|
|
Charlie Phone #: ###-#### okl to cover walls
|
Print Occupancy Form | | | 10/9/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/9/2019 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/13/2019 | 9/9/2019 | 10/8/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 09/02/19 (L-3 - 15 days) (eplan - 90 sheets) Anthony's Restaurant (routed to stafft)
|
Routing - PLAN CHECK | 10/8/2019 | | 10/8/2019 | | PASS |
Carl Westfall
|
|
|
Responsed received via Email
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/8/2019 | | DONE |
|
|
|
ALL MET (cory@yg-construction.com)
NEED
GC
Revised Certificate of Value
|
Routing - PLUMBING | 10/2/2019 | | 10/7/2019 | | PASS |
Daryl Spivey
|
|
|
Installed equipment may require additional backflow protection. Install per plan and ISPC.
|
Routing - PLAN CHECK | 10/4/2019 | | 10/7/2019 | | FAIL |
Carl Westfall
|
|
|
Failed 3rd IBC review. Responses were Emailed outside of ePlanReview. Sent Email response to applicant.
|
Routing - MECHANICAL | 10/2/2019 | | 10/3/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 10/1/2019 | | 10/2/2019 | | FAIL |
Carl Westfall
|
|
|
Some items not resolved. Sent Email to applicant.
|
Routing - Design Review | 10/2/2019 | | 10/2/2019 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00292
|
Plan resubmittals received | | | 10/1/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/18/2019 | 9/21/2019 | 9/18/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 9/18/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 9/18/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/13/2019 | | 9/18/2019 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - FIRE | 8/13/2019 | 8/16/2019 | 9/17/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Environmental | 8/19/2019 | | 9/6/2019 | | PASS |
Rick Christenson
|
|
|
Verify connection to exsiting grease interceptor GW line.
|
Plan Reviewer's activity | | | 8/29/2019 | | DONE |
|
|
|
New projected 1st review done by Sept 16.
|
Routing - MECHANICAL | 8/16/2019 | | 8/22/2019 | | FAIL |
Troy James
|
|
|
Need commissioning form uploaded.
|
Routing - Addressing | 8/16/2019 | | 8/21/2019 | | PASS |
Doug Chausow
|
|
|
UPDATED RESTRAURANT ADDRESS: 959 W Front St
|
Routing - PUBLIC WORKS | 8/16/2019 | | 8/19/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLUMBING | 8/16/2019 | | 8/19/2019 | | PASS |
Daryl Spivey
|
|
|
Installed equipment may requir additional backflow protection.
Install per plan and ISPC
|
Routing - Design Review | 8/16/2019 | | 8/19/2019 | | FAIL |
KayCee Babb
|
|
|
Project shows new rooftop equipment not previously reviewed by Design Review. If units are less than the height of the parapet, no screening is required. Otherwise, screening shall be reviewed and approved by Design Review Staff prior to resubmittal of Building permits.
|
Routing - PLANNING | 8/16/2019 | | 8/16/2019 | | PASS |
David Moser
|
|
|
|
Plan Reviewer's activity | | | 8/13/2019 | | PASS |
|
|
|
Finished and approved the plan intake review.
|
Intake Approval | | | 8/13/2019 | | PASS |
Carl Westfall
|
|
|
|
Intake Approval | | | 8/9/2019 | | FAIL |
|
|
|
(8-8-19) Refer to the circled items in the Plan Intake Checklist. Resolve each item as directed. CJW
|
Application received | | | 8/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 8 2019 4:50PM
|