BLD-Framing/Rough-in | 8/7/2020 | 8/10/2020 | 8/10/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by robert barrow
|
BLD-Conference | 7/31/2020 | 8/3/2020 | 8/3/2020 | P | DONE |
Mike Jordan
|
|
|
Bob *screened* Phone #: ###-####
|
BLD-Footing | 6/30/2020 | 7/1/2020 | 7/1/2020 | A | PEND |
Mike Jordan
|
|
|
bob Phone #: ###-####. Engineer to sign off on epoxy, no special inspection. Aslo need RFI for column pad footings and aditional letter from engineer waiving special inspection on concrete.
|
Plan Reviewer's activity | | | 6/10/2020 | | DONE |
Joe Bruce
|
|
|
Spoke with Bob Barrow regarding the installation of visqueen plastic over exsiting smoke detectors during construction. Since building will not be occupied during construction this is okay per 2015 IFC 901.7. **JHB**
|
Issue PAID IN FULL permit | | | 4/22/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/22/2020 | | DONE |
|
|
|
|
Telephone call | | | 3/25/2020 | | DONE |
|
|
|
email fees to barrowdc@ymail.com
|
Meeting | | | 3/24/2020 | | DONE |
|
|
|
Met- printed fees and emailed//cannot print fees to send to GC will try later today-
|
Telephone call | | | 2/6/2020 | | DONE |
|
|
|
email forward to Joe for extension request see DOC_Email
|
Extend Review Timeline | | | 2/6/2020 | | DONE |
|
|
|
1st approved 180 day extension per joe. see documents
|
Meeting | | | 2/5/2020 | | DONE |
|
|
|
sent email to Jon, justin and joe, informing permit will expire at 5 today 2/5/2020 and may send in an extension request or let me know if the project is no longer going to be done
|
Telephone call | | | 2/5/2020 | | DONE |
|
|
|
extension requestion sent in by justin padleski
|
Plan assigned to (JG) | 8/20/2019 | 8/20/2019 | 10/16/2019 | | PASS |
Javier Guzman
|
|
|
2nd rev L3 Liberty Lake Clubhouse ePlan, pend eng
|
Routing Off Site - STRUCTURAL | 10/9/2019 | | 10/16/2019 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by AHJ Engineers
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/16/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/16/2019 | | DONE |
|
|
|
All met- Need GC
Need Rev Val
|
Routing - PLAN CHECK | 10/9/2019 | | 10/11/2019 | | PASS |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 9/19/2019 | 9/22/2019 | 9/20/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 8/20/2019 | 8/20/2019 | 9/19/2019 | | PASS |
Mark Scharfen
|
|
|
Attached comments to case
|
1st review completed | | | 9/19/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 8/20/2019 | | 9/16/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 8/20/2019 | | 9/14/2019 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by AHJ Engineers
|
Routing - PUBLIC WORKS | 8/20/2019 | | 8/21/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 8/20/2019 | | 8/21/2019 | | PASS |
Michael Zawacki
|
|
|
TI, no ESC needed
|
Routing - PLANNING | 8/20/2019 | | 8/20/2019 | | PASS |
David Moser
|
|
|
see DRH19-00273
|
Routing - Addressing | 8/20/2019 | | 8/20/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - Design Review | 8/20/2019 | | 8/20/2019 | | PASS |
Katelyn Menuge
|
|
|
DRH19-00273
|
Intake Approval | | | 8/16/2019 | | PASS |
|
|
|
|
Intake Approval | | | 8/14/2019 | | FAIL |
Brian McGowan
|
|
|
Please address the following items in order to process your prescreen:
1. Provide a completed Form #310 for Special Inspections.
2. Sheets A101.1, A101.2, A601 and ID100 do not provide the required stamping space in the lwer right hand corner for the City of Boise Approval Stamp. Please revise the sheet layout.
|
Application received | | | 8/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 9 2019 9:55AM
|