Third Notice | | 7/13/2020 | 8/11/2020 | | DONE |
|
|
|
MAILED 8-14-2020 WITH FINAL LETTER
|
Third Follow up | | | 8/11/2020 | | DONE |
|
|
|
|
Third Notice | | 5/12/2020 | 7/8/2020 | | DONE |
|
|
|
mailed 7-9-2020 with second follow up
|
Second Follow up | | | 7/8/2020 | | DONE |
|
|
|
|
Third Notice | | 4/8/2020 | 5/7/2020 | | DONE |
|
|
|
mailed 5-8-2020 with first follow up
|
First Follow up | | | 5/7/2020 | | DONE |
|
|
|
|
Third Notice | | 3/10/2020 | 4/3/2020 | | DONE |
|
|
|
mailed 4-6-2020
|
Third Notice | | 2/12/2020 | 3/5/2020 | | DONE |
|
|
|
mailed 3-6-20
|
Second Notice | | 1/9/2020 | 2/7/2020 | | DONE |
|
|
|
mailed 2-10-20
|
First Notice | | 12/22/2019 | 12/30/2019 | | DONE |
|
|
|
mailed 1-1-20
|
BLD-Final | 12/12/2019 | 12/12/2019 | 12/12/2019 | A | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 12/12/2019 | 12/12/2019 | 12/12/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection for scope of work complete, fire alarm inspection for scope of work is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for scope of work is complete, signatures provided on permit signature card.
|
Permanent Occupancy | | | 12/12/2019 | | DONE |
|
|
|
|
BLD-Final | 12/4/2019 | 12/5/2019 | 12/5/2019 | P | CANC |
Jim Storey
|
|
|
this is for CO . fire life will be inspecting Thursday Please call with any questions. Thank you Phone #: ###-#### Inspection requested via web by Mark Coiner
|
FIRE-Alarm Testing | 12/4/2019 | 12/5/2019 | 12/5/2019 | P | PART |
Jim Page
|
|
|
All emergency lighting tested during this inspection, all fire exitnguishers are in place. Life fire safety cannot be signed off until FIR permit for fire alarms is finaled.
smoke test on 4 exterior RTU''s, ,life safety , EM lite test for full CO Phone #: ###-#### Inspection requested via web by Mark Coiner
|
BLD-Final | 12/3/2019 | 12/4/2019 | 12/4/2019 | A | DEFR |
Jim Storey
|
|
|
this is for CO . fire life will be inspecting Thursday Please call with any questions. Thank you Phone #: ###-#### Inspection requested via web by Mark Coiner voice mail full need fire and plm insp to be complet pend ing. rolled insp to pm thursday.
|
FIRE-Final Inspection | 10/31/2019 | 10/31/2019 | 10/31/2019 | A | PART |
Jim Page
|
|
|
Fire sprinkler inspection for office area is complete (Office scope FIR permit is finaled), fire alarm inspection for TCO is complete (have items that need to be inspected after permenant power is established), fire extinguishers are placed with current inspection tags. Per conversation with Ron Johnson, TCO for life fire safety is autorized for 90 days, signatures provided on signature card for temporary occupancy.
fire sprinkler spray issues were resolved, 2 heads changed out , and EM''s are installed as per design. If possible a 10-12 noon inspection is requested. Thank you Phone #: ###-#### Inspection requested via web by Mark Coiner
|
Temporary Occupancy | 10/31/2019 | 1/29/2020 | 10/31/2019 | | DONE |
Tiffany Carson-Herker
|
|
|
|
BLD-Final | 10/29/2019 | 10/29/2019 | 10/29/2019 | P | PART |
Jim Storey
|
|
|
TCO building inspection fire inspection requested today also. Phone #: ###-#### Inspection requested via web by Mark Coiner tco ok upon fire sign off.
|
FIRE-Final Inspection | 10/28/2019 | 10/29/2019 | 10/29/2019 | P | FAIL |
Jim Page
|
|
|
Emergency lighting does not match the city approved drawings. FIR permit for fire sprinkler in office remodel area needs to be finaled before TCO.
Final inspection for TCO, fire life inspection Phone #: ###-#### Inspection requested via web by Mark Coiner
|
BLD-Final | 10/22/2019 | 10/25/2019 | 10/25/2019 | A | NR |
Jim Storey
|
|
|
For TCO Phone #: ###-#### Inspection requested via web by Mark Coiner
|
BLD-Ceiling Grid Inspection | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Coiner// mains need wire support 8 inches from ends// pending trades.
|
Zoning Approval | 10/16/2019 | 10/16/2019 | 10/16/2019 | | DONE |
Katelyn Menuge
|
|
|
No inspection needed for Planning
|
BLD-Framing/Rough-in | 10/1/2019 | 10/3/2019 | 10/3/2019 | A | PASS |
Jim Storey
|
|
|
early am requested...thank you Phone #: ###-#### Inspection requested via web by Mark Coiner
|
BLD-Energy code compliance | 10/3/2019 | 10/3/2019 | 10/3/2019 | A | PASS |
Jim Storey
|
|
|
early am requested...thank you Phone #: ###-#### Inspection requested via web by Mark Coiner roof and walls insulation complet and aproved.
|
BLD-Framing/Rough-in | 9/30/2019 | 10/2/2019 | 10/1/2019 | A | CANC |
Jim Storey
|
|
|
MEP rough in inspections should be completed by 10-2-2019 Phone #: ###-#### >> Inspection requested via web by Mark Coiner Inspection cancelled from web by: Mark Coiner
|
Issue PAID IN FULL permit | | | 9/30/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/30/2019 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 8/29/2019 | 8/29/2019 | 9/26/2019 | | PASS |
Carl D Madsen
|
|
|
D1D2
|
Routing Off Site - STRUCTURAL | 9/23/2019 | | 9/26/2019 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/26/2019 | | DONE |
|
|
|
all met-pleae close the early start permit and if needed move the sub permits to this BLD permit-Need GC-met
Need rev cert of val-met
called John Gerlach to let know we need the 302 & 306 forms
|
Routing - PLAN CHECK | 9/14/2019 | | 9/20/2019 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 9/14/2019 | | 9/20/2019 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 8/28/2019 | | 9/14/2019 | | FAIL |
Carl D Madsen
|
|
|
ahj
|
Route to Impact Fee Review | 9/10/2019 | 9/13/2019 | 9/11/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 8/28/2019 | 8/28/2019 | 9/3/2019 | | PASS |
Mark Scharfen
|
|
|
09/03 DID2 small ti review complete. No racking on this permit. Site will not use powered industrical trucks, only hand carts. No report uploaded.
|
1st review completed | | | 9/3/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 8/28/2019 | | 9/3/2019 | | PASS |
Troy James
|
|
|
|
Plan assigned to (CJW) | 8/28/2019 | 8/28/2019 | 8/29/2019 | | DEFR |
Carl Westfall
|
|
|
09/09 L2 DID2 ePlan
|
Routing - PLAN CHECK | 8/28/2019 | | 8/29/2019 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLUMBING | 8/28/2019 | | 8/29/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC
|
Routing - Addressing | 8/28/2019 | | 8/28/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/28/2019 | | 8/28/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Design Review | 8/28/2019 | | 8/28/2019 | | PASS |
Katelyn Menuge
|
|
|
DRH19-00349
|
Plan Reviewer's activity | | | 8/27/2019 | | |
Brian McGowan
|
|
|
Applicant removed the Smopker's Shelter from the Scope of Work. Will submit as a new Permit or Plan Modification.
|
Intake Approval | | | 8/27/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 8/23/2019 | | FAIL |
Brian McGowan
|
|
|
Please address the following items in order for your Prescreen to be approved:
1. COMcheck did not have values on the uploaded pages.
2. Provide the engineering for the Pre-Engineered smoker's shelter.
3. Planning and Zoning Approval letters for the Smoker's Shelter. Contact KayCee Babb at ###-#### if you have any questions on the submittal requirements.
Any page resubmitted must be renamed exactly as the page it is intended to replace. This includes all Mechanical, Electrical, Plumbing and Civil Sheets.
|
Intake Approval | | | 8/14/2019 | | FAIL |
Brian McGowan
|
|
|
Please address the following items in order for your Prescreen to be approved:
1. COMcheck di not have values on the uploaded pages.
2. All Plan Sheets must provide the appropriate room for the City of Boise Approval Stamp.
3. Document DIDs PDS #304 signed was uploaded as a 38.2"x49.2" sheet. Please revise to an 8.5 x 11
4. Provide a completed Form #310 for Special Inspections.
5. Provide Information on the Pre-Engineered smoker's shelter as well as the engineering.
6. Planning and Zoning Approval letters for the Smoker's Shelter.
|
Application received | | | 8/10/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 10 2019 1:11PM
|
Third Notice | | 8/16/2020 | | | |
|
|
|
|