BLD-Final | 9/9/2019 | 9/12/2019 | 9/12/2019 | P | PASS |
Dave Hannah
|
|
|
MAIN CONTACT: BRIAN PRUSSIA - ###-#### On-Site Contact - Mierins Rozentals: ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting
|
DOC - Permit Finaled | 9/12/2019 | 9/12/2019 | 9/12/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 9/6/2019 | 9/10/2019 | 9/9/2019 | P | CANC |
Dave Hannah
|
|
|
On-Site Contact - Brian Prussia: ###-####& & Mierins Rozentals: ###-#### Please call ahead. Thank you!
<> Install Crew Lead - Jeremy Walters: ###-#### <> Electrician - Shaun Shafer: ###-#### Phone #: ###-#### >> Inspection requested via web by BRS Permitting Inspection cancelled from web by: BRS Permitting
|
BLD-Framing/Rough-in | 8/28/2019 | 8/29/2019 | 8/29/2019 | A | NR |
Dave Hannah
|
|
|
Jay Walters is best contact Phone #: ###-#### Inspection requested via web by BRS Permitting
|
Issue PAID IN FULL permit | | | 8/16/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 8/12/2019 | 8/12/2019 | 8/15/2019 | | PASS |
Josh Bogle
|
|
|
08/16 PV, ePlan
|
Routing - PLAN CHECK | 8/12/2019 | | 8/15/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 8/15/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 8/15/2019 | | DONE |
|
|
|
|
Application received | | | 8/12/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 12 2019 2:19PM
|
Plans ACCEPTED BY PLAN TECH | | | 8/12/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/12/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/12/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 8/12/2019 | | 8/12/2019 | | PASS |
Jeff Lowe
|
|
|
|