BLD-Final | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | PASS |
Tell Riley
|
|
|
Garage code 3162 Phone #: ###-#### Inspection requested via web by Kelly Stover//corrections made//
|
DOC - Permit Finaled | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Blower Door Test Results | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | DONE |
Tell Riley
|
|
|
3.82 ACH 50
|
BLD-Final | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | NR |
Tell Riley
|
|
|
Garage code 3162 Phone #: ###-#### Inspection requested via web by Kelly Stover//need to add carbon smoke combo as discussed//add insulatio to crawl access//fix down insulation in crawl//
|
BLD-Energy code compliance | 10/29/2019 | 10/29/2019 | 10/29/2019 | P | PASS |
Tell Riley
|
|
|
Mark Phone #: ###-####
|
BLD-Framing/Rough-in | 10/29/2019 | 10/29/2019 | 10/29/2019 | P | PASS |
Tell Riley
|
|
|
Mark Phone #: ###-####//corrections made//
|
BLD-Framing/Rough-in | 10/25/2019 | 10/25/2019 | 10/25/2019 | P | FAIL |
Tell Riley
|
|
|
MARK Phone #: ###-####//need to add header at bay window per plans//need truss plans onsite//
|
BLD-Wall Bracing | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
BLD-Foundation | 9/5/2019 | 9/6/2019 | 9/6/2019 | A | PASS |
Tell Riley
|
|
|
mark- poring is at 12:45 Phone #: ###-####
|
BLD-Footing | 9/4/2019 | 9/5/2019 | 9/5/2019 | P | PASS |
Tell Riley
|
|
|
215 pour .. Mark Phone #: ###-####
|
BLD-Footing | 9/4/2019 | 9/4/2019 | 9/4/2019 | P | CANC |
Tell Riley
|
|
|
245 pour .. Mark Phone #: ###-####//cancel per mark//
|
Issue PAID IN FULL permit | | | 8/29/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/29/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/29/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 8/28/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 8/14/2019 | 8/14/2019 | 8/28/2019 | | DONE |
Rob Patrick
|
|
|
08/28 sfd L1 ePlan
|
Routing - PLAN CHECK | 8/14/2019 | | 8/28/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 8/28/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/28/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 8/28/2019 | | DONE |
|
|
|
met
|
Route to Impact Fee Review | 8/14/2019 | 8/17/2019 | 8/15/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Intake Approval | | | 8/14/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/14/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 8/14/2019 | | 8/14/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/14/2019 | | 8/14/2019 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 8/14/2019 | | 8/14/2019 | | PASS |
Doug Chausow
|
|
|
Address: 9650 W Macaw St
|
Routing - PUBLIC WORKS | 8/14/2019 | | 8/14/2019 | | PASS |
Angela Hardy
|
|
|
|
Application received | | | 8/12/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 12 2019 4:57PM
|