Permanent Occupancy | | | 12/10/2019 | | DONE |
|
|
|
|
BLD-Final | 10/3/2019 | 10/4/2019 | 10/4/2019 | A | PASS |
Mike Jordan
|
|
|
josh Phone #: ###-####. OK for perm occ.
|
FIRE-Final Inspection | 10/3/2019 | 10/3/2019 | 10/3/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per plan review the single door out of the exterior of the warehouse, as shown on the plans, is not required. josh Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/17/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 8/20/2019 | 8/20/2019 | 8/26/2019 | | DONE |
Julie Romig
|
|
|
08/26 - IBC Rev Comp - 528 Mountain Pacific Machinery
|
1st review completed | | | 8/26/2019 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/26/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/26/2019 | | DONE |
|
|
|
|
Telephone call | | | 8/26/2019 | | DONE |
|
|
|
no work done under this permit, so I took out the requirement for a revised certificate of value and a gc form. This is a 528 application
|
Routing - FIRE | | 8/20/2019 | 8/23/2019 | | PASS |
Mark Scharfen
|
|
|
08/26-Mountain Pacific Machinery Occupancy review complete 08.23.2019. No report, no hazardous materials or high piled storage in warehouse.
|
Case Summary (BLD) | | | 8/22/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | | | 8/22/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - Addressing | 8/20/2019 | | 8/22/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/20/2019 | | 8/22/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/20/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/20/2019 | | PASS |
Julie Romig
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/20/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/19/2019 | | FAIL |
Brian McGowan
|
|
|
528- Occupancy Permits cannot be done online, it must be done in person. The previous or current Certificate of Occupancy and Floor Plan on File must be provided. The proposed floor plan needs to match the existing floor plan on file.
|
Intake Approval | | | 8/14/2019 | | FAIL |
Brian McGowan
|
|
|
Please address the following items for your Prescreen to be approved:
1. Verify the address. I had the Pemit Tech change the address to 6141 W. Corporal Ln. There is a 6133 Corporal Ln but not a 6133 Clinton.
2. Are you using the 528 application or the 518 Application? Both were uploaded. Please provide the required information as requested by the Checklists.
3. Provide a layout of the Storage Area showing shelves, racks, aisles.
4. A1.1 has no notations.
5. Verify the Occupant load (See IBC 2902.2) Plumbing fixtures may be an issue.
|
Application received | | | 8/13/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 13 2019 10:18AM
|
First Notice | | 12/20/2019 | | | |
|
|
|
|