BLD-Final | 11/12/2019 | 11/12/2019 | 11/12/2019 | P | PASS |
Tell Riley
|
|
|
Gary Phone #: ###-####//framing corrections made//final complete//
|
DOC - Permit Finaled | 11/12/2019 | 11/12/2019 | 11/12/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Framing/Rough-in | 10/25/2019 | 10/28/2019 | 10/28/2019 | P | PART |
Tell Riley
|
|
|
Gary Phone #: ###-####//need to add truss clips and anchor bolts at plate ends//
|
BLD-Wall Bracing | 10/4/2019 | 10/7/2019 | 10/7/2019 | A | PART |
Tell Riley
|
|
|
Gary Phone #: ###-####//nailing ok for exterior walls//discuss approval of hold downs with engineer//interior shear wall is gypsum board and not yet installed//
|
BLD-Wall Bracing | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | FAIL |
Tell Riley
|
|
|
shear // Gary Phone #: ###-####//need to verify hold downs with engineer--STHD 14 specified and not used//nail shear walls or provide alternative from engineer//portal frame needs nailed 3" oc//
|
BLD-Foundation | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | PASS |
Tell Riley
|
|
|
Gary Phone #: ###-####
|
BLD-Footing | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Tell Riley
|
|
|
Gary Phone #: ###-####//per plans//
|
Routing Walk-In (Zoning) | 8/15/2019 | 8/15/2019 | 8/15/2019 | A | PASS |
Ethan Mansfield
|
|
|
|
Routing Walk-In (BLD) | 8/15/2019 | 8/15/2019 | 8/15/2019 | A | DONE |
Rob Patrick
|
|
|
|
Plan assigned to (RDP) | 8/15/2019 | 8/15/2019 | 8/15/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 8/15/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/15/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/15/2019 | | 8/15/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 8/15/2019 | | DONE |
Rob Patrick
|
|
|
|
Inspection Record Card- Bld | | | 8/15/2019 | | DONE |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 8/15/2019 | | DONE |
Rob Patrick
|
|
|
|
Application received | | 8/15/2019 | | | |
|
|
|
|