Second Notice | | 7/19/2020 | 7/31/2020 | | DONE |
|
|
|
This permit finaled on the web by Tom Raistrick
|
First Notice | 5/26/2020 | 5/26/2020 | 7/9/2020 | | DONE |
Jim Storey
|
|
|
mailed 7-9-2020
|
BLD-Final | 5/25/2020 | 5/26/2020 | 5/26/2020 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Raistrick
|
DOC - Permit Finaled | 5/26/2020 | 5/26/2020 | 5/26/2020 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 5/15/2020 | 5/19/2020 | 5/19/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Phone #: ###-#### Inspection requested via web by Tom Raistrick
|
Plan assigned to (BJM) | 1/3/2020 | 1/3/2020 | 1/3/2020 | | DONE |
Brian McGowan
|
|
|
|
Plan Reviewer's activity | | | 1/3/2020 | | DONE |
Brian McGowan
|
|
|
The Permit should be for the core building on the second floor and should not have a Suite number. The Suite number will be deleted from the Permit.
|
Meeting | | | 1/3/2020 | | DONE |
|
|
|
Spoke with Tisha and Brian. Per applicant plan mod request, removed the ste number from the application in ePlan, and changed the address on the BLD and all attached cases. See plan mod in DOCS
|
Plan Modification Accepted | | | 1/3/2020 | | DONE |
|
|
|
plan mod requested by Glenn Walker to change the address of the case to eliminate the suite number
|
Plan Reviewer's activity | | | 1/2/2020 | | DONE |
Brian McGowan
|
|
|
Contractor called requesting the Ste 100 be stricken from the Permit based on the scope of work was for the bathrooms that service the common area of the 2nd floor, not Ste 100.
I called Glenn Walker and asked him to submit a Plan Modification to the addressing. Returned a call to Tom, the contractor, letting him know the process and that I called Glen and left a message.
|
BLD-Framing/Rough-in | 12/26/2019 | 12/27/2019 | 12/27/2019 | A | PASS |
Brandon Shaw
|
|
|
2nd floor restroom // Tom Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/10/2019 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 8/27/2019 | 8/27/2019 | 10/23/2019 | | DONE |
Brian McGowan
|
|
|
10/27-1st Review Complete- Oak Park Plaza Restrooms ePlan
|
Routing - PLAN CHECK | 10/23/2019 | | 10/23/2019 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 10/23/2019 | | DONE |
|
|
|
Need GC
Need Rev Val
|
Route to Impact Fee Review | 10/16/2019 | 10/19/2019 | 10/18/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 8/27/2019 | | 10/16/2019 | | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 10/16/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PUBLIC WORKS | 8/27/2019 | | 8/27/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 8/27/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 8/16/2019 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
• Per ePlan submittal standards the reserve the bottom right corner for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block on plan sheet A0.2 (see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf )
|
Application received | | | 8/15/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 15 2019 7:13PM
|