Permit Information
Permit NumberBLD19-03153
StatusIssued
Name JULIETTE JENNINGS
Site Address 908 N 10TH ST Unit: 110
Project NameADU 908 10th avenue
Customer NumberCAA19-00141
ePlanReviewYes
Description
Permit for an addition of a bathroom w/ shower and kitchen area to existing bonus room above detached garage to create Accessory Dwelling Unit. Installation of new skylight and insulation in compliance with energy code. Ref BLD13-02576 for original construction of detached garage and storage space above.**RDP***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/3/20208/4/20208/5/2020AFAIL
DetailsDave Hannah
ok with video/photo // Shane Phone #: ###-#### needs to fix windows max 4inchs smoke dector handrail and gaurdrail
BLD-Framing/Rough-in5/14/20205/14/20205/14/2020PPASS
DetailsDave Hannah
Shane Phone #: ###-####
Inspection Record Card- Bld  12/31/2019 DONE
Issue PAID IN FULL permit  12/31/2019 DONE
Meeting  11/19/2019 DONE
parcel owner came in to change permit BLD19-03153 and all attached permits to her name see Document Letter, GC ACNS is no longer doing work, parcel owner took over Eplan, parcel owner will be hire a new GC -ok by Tisha
Route to Impact Fee Review9/19/20199/22/201911/18/2019 PASS
DetailsTravis P Black
Initial residential review of new SFD permits requested for now.
Permit Ready to Issue  11/13/2019 DONE
Plan Reviewer's activity  11/13/2019 DONE
DetailsBrian McGowan
No to ESC
Yes to Energy
Plan assigned to (J_N)11/12/201911/12/201911/12/2019 DONE
DetailsJenny Nelson
waiting for planning sign off in eplan
Plan assigned to (RDP)9/19/20199/19/201911/12/2019 DEFR
DetailsRob Patrick
10/02 ADU L2 ePlan...10/08 Failed
Routing - PLANNING9/19/2019 11/12/2019 FAIL
DetailsEthan Mansfield
Deed restriction required.
PLANS/APPL TAKEN TO FRONT DESK  11/12/2019 DONE
DetailsJenny Nelson
Routing - PLANNING11/12/2019 11/12/2019 PASS
DetailsEthan Mansfield
Deed restriction submitted.
Routing - PLAN CHECK11/12/2019 11/12/2019 PASS
DetailsJenny Nelson
Ready to pass when planning passes per RDP
Routing - PLAN CHECK11/6/2019 11/6/2019 FAIL
DetailsRob Patrick
Failed per Planning Comments: Building Review is complete and ready to Pass.
Routing - PLAN CHECK10/11/2019 10/11/2019 FAIL
DetailsRob Patrick
Corrections Required
1st review completed  10/8/2019 FAIL
DetailsRob Patrick
Corrections Req'd
Routing - PLAN CHECK9/19/2019 10/8/2019 FAIL
DetailsRob Patrick
Corrections Req'd
Routing - Addressing9/19/2019 9/23/2019 PASS
DetailsDoug Chausow
Primary home must be addressed as 908 N 10th St, Unit 100, ADU as 908 N 10th St, Unit 110
Routing - PUBLIC WORKS9/19/2019 9/23/2019 PASS
DetailsMorgan Webb
Routing - MECHANICAL9/19/2019 9/19/2019 PASS
DetailsTroy James
Need minimum 50 cfm bath fan exhaust to the exterior.
Intake Approval  9/19/2019 PASS
no fees paid at intake
Intake Approval  9/19/2019 PASS
Override - Parcel Holds  9/19/2019  
Recd Pcfee & Taken To Pln CK  9/19/2019 DONE
no fees paid at intake
Application received  8/16/2019 DONE
Application submitted via PDS Online on Aug 16 2019 3:45PM