BLD-Foundation | 7/2/2020 | 7/6/2020 | 7/6/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 7/2/2020 | 7/2/2020 | 7/2/2020 | P | PASS |
Brandon Shaw
|
|
|
Justin *screened* Phone #: ###-####
|
BLD-Footing | 6/30/2020 | 7/1/2020 | 7/1/2020 | A | FAIL |
Brandon Shaw
|
|
|
Not ready
|
BLD-Footing | 6/29/2020 | 6/30/2020 | 6/30/2020 | A | NR |
Jim Storey
|
|
|
Pat - Late Am if possible Phone #: ###-####
|
BLD-Footing | 6/26/2020 | 6/29/2020 | 6/29/2020 | A | NR |
Brandon Shaw
|
|
|
Pat Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/18/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/18/2020 | | DONE |
|
|
|
|
Telephone call | | | 6/17/2020 | | DONE |
|
|
|
Emailed the GC the 302 to fill out.
|
Extend Review Timeline | | | 3/19/2020 | | DONE |
|
|
|
1st approved 180 day extension per joe. see documents
|
Meeting | | | 3/18/2020 | | DONE |
|
|
|
forward email requesting to Joe
|
Telephone call | | | 3/17/2020 | | DONE |
|
|
|
sent final email informing permit is past date and will need to send in an extension request by 5pm of 3-20-2020
|
Telephone call | | | 2/24/2020 | | DONE |
|
|
|
emailed kyle, tony and tyler that this permit is 9 days past the date and that he may still send in a request for an extension
|
Meeting | | | 2/5/2020 | | DONE |
|
|
|
emailed kyle, tony and tyler that permit will expire in 15 days 2/15/2020
|
OVERRIDE | | | 10/24/2019 | | |
|
|
|
|
Routing - FIRE | 10/24/2019 | 10/24/2019 | 10/24/2019 | | PASS |
Lee G Meredith
|
|
|
Kyle Lepper provided a driveway waiver for possible fire aparatus damage. No sprinklers required.
|
Plan assigned to (RDP) | 8/20/2019 | 8/20/2019 | 10/24/2019 | | DONE |
Rob Patrick
|
|
|
09/02 sfd L1 ePlan...10/16 Failed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 10/24/2019 | | DONE |
|
|
|
met
Need GC
|
Routing - PLAN CHECK | 10/24/2019 | | 10/24/2019 | | PASS |
Rob Patrick
|
|
|
|
Telephone call | | | 9/27/2019 | | DONE |
|
|
|
Discussed fire code requriements with architect Kyle Lepper. Informed him that if he provides a waver that holds the fire department harmless for damage to his driveway, fire code review can be approved. He agreed and will email it to me.
This same information was provided to Keath Bennett via email at 11:40 am on 9-30-19.
|
Routing - FIRE | 8/29/2019 | 8/29/2019 | 8/30/2019 | | FAIL |
Mark Scharfen
|
|
|
08/30-322 Pensilvania Flag Lot-review complete. Uploaded and emailed architect rev_fire 08.30.2019.pdf. Flag lot, will need sprinklers-FD Access/no Suez report.
Received a waver from the owner that holds the fire department harmless if damage occurs from fire department's need ot use the driveway.
|
1st review completed | | | 8/29/2019 | | FAIL |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 8/20/2019 | | 8/29/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd. Braced Wall corrections
|
Routing - PUBLIC WORKS | 8/20/2019 | | 8/22/2019 | | PASS |
Angela Hardy
|
|
|
|
Route to Impact Fee Review | 8/20/2019 | 8/23/2019 | 8/21/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 8/20/2019 | | 8/21/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 8/20/2019 | | 8/20/2019 | | PASS |
Ethan Mansfield
|
|
|
|
Routing - Addressing | 8/20/2019 | | 8/20/2019 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 8/20/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/20/2019 | | DONE |
|
|
|
|
Application received | | | 8/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 19 2019 5:46AM
|