BLD-Final | 5/13/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Brandon Shaw
|
|
|
Pool only...
|
DOC - Permit Finaled | 5/14/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 4/23/2020 | 4/23/2020 | 4/23/2020 | | DEFR |
Brandon Shaw
|
|
|
|
Extend Permit 90/180 days | 4/23/2020 | 4/23/2020 | 4/23/2020 | P | DONE |
Brandon Shaw
|
|
|
|
BLD-Footing | 12/11/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Brandon Shaw
|
|
|
Mark Phone #: ###-####
|
PubWorks Subgrade Approval | 12/11/2019 | 12/11/2019 | 12/11/2019 | | DONE |
Melissa Jannusch
|
|
|
POOL A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 9/11/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 8/22/2019 | 8/22/2019 | 9/4/2019 | | PASS |
Josh Bogle
|
|
|
08/28 pool, paper
|
1st review completed | | | 9/4/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 9/4/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 9/4/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 9/4/2019 | | DONE |
|
|
|
Need
GC Form
|
Telephone call | | | 9/4/2019 | | DONE |
|
|
|
Left voicemail for Lance to inform him the permit is ready and what fees are due.
|
Routing - PLAN CHECK | | | 9/3/2019 | | PASS |
Josh Bogle
|
|
|
|
Routing - Erosion and Sediment | | | 9/3/2019 | | PASS |
Andy J. Long
|
|
|
will use existing site ESC plan. Must contain concrete or gypcrete washout and dispose of properly.
|
Routing PW Grading-Hillside | 8/29/2019 | | 8/29/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable must be approved by Public Works prior to scheduling inspections. Please allow 24 hours for subgrade approval processing. If you have any questions call Melissa Jannusch ###-####.
|
Routing - PLANNING | 8/29/2019 | | 8/29/2019 | | PASS |
Jeff Lowe
|
|
|
POOL ONLY
|
Routing - Addressing | 8/23/2019 | | 8/23/2019 | | PASS |
Doug Chausow
|
|
|
|
Telephone call | | | 8/22/2019 | | DONE |
|
|
|
called Andy L to see if he was ok with us using the same ESC permit as the grading and new SFD since they are all the same people
|
Intake Approval | | | 8/22/2019 | | PASS |
|
|
|
cat 1 approved by MMJ
|
Recd Pcfee & Taken To Pln CK | | | 8/22/2019 | | DONE |
|
|
|
no fees paid at intake
|
Application received | | 8/22/2019 | | | |
|
|
|
|