Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD19-03238
StatusIssued
Name OPUS DESIGN BUILD LLC
Site Address 412 S 3RD ST
Project Name3rd & Myrtle Shell/Core
Customer NumberBLD19-04432
ePlanReviewYes
Description
***GREEN TAG-PRIORTY REVIEW-PROJET MANAGEMENT-Angie Brosious*** (3RD & MYRTLE) (SHELL/CORE ONLY) (DRH19-00007) (GRD19-00067 Grading/Utilities) (BLD19-02943 Foundation) Permit to construct the shell and core of the Type IA podium and the Type IIIA building above for an 8-story, mixed-use residential housing project. Work to include: construction of Type IA podium including foundation, structural steel, PT concrete slab and exterior walls; construction of Type IIIA structure including wood framed exterior walls, floors, roof, and interior bearing walls; construction of interior core including stair, elevator, and mechanical shafts. Special inspections required per the attached Form 310. Special Inspection survey required to verify low point of grade at beginning of construction, building height of top of podium, 5th flr, and 8th flr at framing stage, at 8th flr final construction. Deferred submittals as listed on G0.01. Approval contingent upon adhering to the approved plans on file and attached engineering. This building will be sprinklered with a fully compliant NFPA 13 and NFPA fire alarm system for occupancy, allowable area increase, and height increase. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Conference8/6/20208/6/20208/6/2020ADONE
DetailsJim Page
Fire conference is complete. As discussed the temporary standpipe for fire protection needs to comply with section 3313 of the 2015 IFC, as of this entry, the standpipe only goes to level 4 of the parking garage. Means of egress needs to comply with section 3311 of the 2015 IFC as well. Standpipe must meet the requirements mentioned by 12AUG2020 or a stop work will be placed on the project until the requirements are met.
BLD-Framing/Rough-in7/29/20207/30/20207/30/2020APART
DetailsDave Hannah
Joe Phone #: ###-#### ok steel studs 1st 2nd and 3rd ok mto prerock and insulate
BLD-Framing/Rough-in6/17/20206/18/20206/18/2020PPART
DetailsDave Hannah
screened // joe Phone #: 208-###-#### second and third floor ext steel stud framing ok to sheet ext
Telephone call  12/31/2019 DONE
email sent to- Tim.Callahan@opus-group.com to inform him that we need the 302, ACHD and RP before permit is issue
Telephone call  12/31/2019 DONE
Tim Callahan emailed in the form 302 and gave us RP
Issue PAID IN FULL permit  12/31/2019 DONE
Inspection Record Card- Bld  12/31/2019 DONE
MISC ACTIONS  12/31/2019 DONE
Address changed from 200 W. Myrtle to 412 S. 3rd St. per Public Works Addressing.
Inspection Record Card- Bld  12/31/2019 DONE
Plan assigned to (JAR)9/18/20199/18/201912/20/2019 DONE
DetailsJulie Romig
12/13 (5 days) - 3rd Rev - 1st Rev Comp - **GREEN TAG** 3rd & Myrtle Shell/Core
Routing - PLAN CHECK12/9/2019 12/20/2019 PASS
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  12/20/2019 DONE
Permit Ready to Issue  12/20/2019 DONE
GC is applicant

Need RP
MET- Need ACHD
Need GC
Routing - FIRE12/16/201912/16/201912/16/2019 PASS
DetailsErika Akin
Attached comments to case
Routing - FIRE11/12/201911/12/201911/20/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - PLAN CHECK11/12/2019 11/19/2019 FAIL
DetailsJulie Romig
2nd Review - see IBC Plan Review Report in ePlanReview for corrections.
Routing PW Street Lights11/12/2019 11/18/2019 PASS
DetailsTom Marshall
Routing - PLANNING11/15/2019 11/15/2019 PASS
DetailsCody Riddle
Sustainability doucments incldued in BLD resubmittal.
Routing Off Site - STRUCTURAL11/12/2019 11/14/2019 PASS
DetailsJulie Romig
Routing - MECHANICAL11/12/2019 11/13/2019 PASS
DetailsTroy James
Routing - Design Review11/12/2019 11/13/2019 PASS
DetailsJosh Wilson
ROS recorded
Routing - Addressing11/12/2019 11/12/2019 PASS
DetailsDoug Chausow
Route to Impact Fee Review10/18/201910/21/201910/22/2019 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE9/18/20199/18/201910/18/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - PLAN CHECK9/18/2019 10/18/2019 FAIL
DetailsJulie Romig
1st review completed  10/18/2019 DONE
DetailsJulie Romig
Routing Off Site - STRUCTURAL9/18/2019 10/3/2019 FAIL
DetailsJulie Romig
Jacobs (CH2M Hill)
Routing - Design Review9/18/2019 10/2/2019 FAIL
DetailsJosh Wilson
DR Modification (DRH19-00383) appeal period effective until 10/12/19.
Routing PW Environmental9/19/2019 10/1/2019 PASS
DetailsRick Christenson
No Grease Interceptor shown not approved for resturant/coffee shop due to no grease abatement.
Routing PW Drainage9/19/2019 9/27/2019 PASS
DetailsBrian Murphy
Routing - Erosion and Sediment9/18/2019 9/23/2019 PASS
DetailsAndy J. Long
Main ESC permit is ESC19-00292 - to be issued with site development and grading permit GRD19-00067
Routing - MECHANICAL9/18/2019 9/23/2019 FAIL
DetailsTroy James
See eplan
Routing - PLANNING9/18/2019 9/19/2019 FAIL
DetailsCody Riddle
The development agreement (CAR18-00021) required the developer explore sustainability measures (Section 5). A detailed summary of this effort, including specifics on what features are included, is required before issuance of building permits.
Routing - PUBLIC WORKS9/18/2019 9/19/2019 PASS
DetailsMorgan Webb
Routing PW Sewer Rating9/19/2019 9/19/2019 PASS
DetailsMorgan Webb
TRUNK AND TREATMENT WILL BE ASSESSED WITH FULL BUILD OUT. ASSESSMENT CHARGED WITH BLD19-02943
Routing PW Street Lights9/19/2019 9/19/2019 FAIL
DetailsTom Marshall
Routing PW Sewer Design9/19/2019 9/19/2019 PASS
DetailsDeAnn Brown
Sewer connection approved under associated grading permit.
Routing PW Solid Waste9/19/2019 9/19/2019 PASS
DetailsEvan Carpenter
Routing - Addressing9/18/2019 9/18/2019 FAIL
DetailsDoug Chausow
Parcels must be consolidated before permit can be issued.
Routing - PLUMBING9/18/2019 9/18/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Intake Approval  9/18/2019 PASS
DetailsJulie Romig
Application received  8/22/2019 DONE
Application submitted via PDS Online on Aug 22 2019 1:16PM