FIRE-Conference | 8/6/2020 | 8/6/2020 | 8/6/2020 | A | DONE |
Jim Page
|
|
|
Fire conference is complete. As discussed the temporary standpipe for fire protection needs to comply with section 3313 of the 2015 IFC, as of this entry, the standpipe only goes to level 4 of the parking garage. Means of egress needs to comply with section 3311 of the 2015 IFC as well. Standpipe must meet the requirements mentioned by 12AUG2020 or a stop work will be placed on the project until the requirements are met.
|
BLD-Framing/Rough-in | 7/29/2020 | 7/30/2020 | 7/30/2020 | A | PART |
Dave Hannah
|
|
|
Joe Phone #: ###-#### ok steel studs 1st 2nd and 3rd ok mto prerock and insulate
|
BLD-Framing/Rough-in | 6/17/2020 | 6/18/2020 | 6/18/2020 | P | PART |
Dave Hannah
|
|
|
screened // joe Phone #: 208-###-#### second and third floor ext steel stud framing ok to sheet ext
|
Telephone call | | | 12/31/2019 | | DONE |
|
|
|
email sent to- Tim.Callahan@opus-group.com to inform him that we need the 302, ACHD and RP before permit is issue
|
Telephone call | | | 12/31/2019 | | DONE |
|
|
|
Tim Callahan emailed in the form 302 and gave us RP
|
Issue PAID IN FULL permit | | | 12/31/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/31/2019 | | DONE |
|
|
|
|
MISC ACTIONS | | | 12/31/2019 | | DONE |
|
|
|
Address changed from 200 W. Myrtle to 412 S. 3rd St. per Public Works Addressing.
|
Inspection Record Card- Bld | | | 12/31/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 9/18/2019 | 9/18/2019 | 12/20/2019 | | DONE |
Julie Romig
|
|
|
12/13 (5 days) - 3rd Rev - 1st Rev Comp - **GREEN TAG** 3rd & Myrtle Shell/Core
|
Routing - PLAN CHECK | 12/9/2019 | | 12/20/2019 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/20/2019 | | DONE |
|
|
|
GC is applicant
Need RP
MET- Need ACHD
Need GC
|
Routing - FIRE | 12/16/2019 | 12/16/2019 | 12/16/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - FIRE | 11/12/2019 | 11/12/2019 | 11/20/2019 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing - PLAN CHECK | 11/12/2019 | | 11/19/2019 | | FAIL |
Julie Romig
|
|
|
2nd Review - see IBC Plan Review Report in ePlanReview for corrections.
|
Routing PW Street Lights | 11/12/2019 | | 11/18/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLANNING | 11/15/2019 | | 11/15/2019 | | PASS |
Cody Riddle
|
|
|
Sustainability doucments incldued in BLD resubmittal.
|
Routing Off Site - STRUCTURAL | 11/12/2019 | | 11/14/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 11/12/2019 | | 11/13/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 11/12/2019 | | 11/13/2019 | | PASS |
Josh Wilson
|
|
|
ROS recorded
|
Routing - Addressing | 11/12/2019 | | 11/12/2019 | | PASS |
Doug Chausow
|
|
|
|
Route to Impact Fee Review | 10/18/2019 | 10/21/2019 | 10/22/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 9/18/2019 | 9/18/2019 | 10/18/2019 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing - PLAN CHECK | 9/18/2019 | | 10/18/2019 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 10/18/2019 | | DONE |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 9/18/2019 | | 10/3/2019 | | FAIL |
Julie Romig
|
|
|
Jacobs (CH2M Hill)
|
Routing - Design Review | 9/18/2019 | | 10/2/2019 | | FAIL |
Josh Wilson
|
|
|
DR Modification (DRH19-00383) appeal period effective until 10/12/19.
|
Routing PW Environmental | 9/19/2019 | | 10/1/2019 | | PASS |
Rick Christenson
|
|
|
No Grease Interceptor shown not approved for resturant/coffee shop due to no grease abatement.
|
Routing PW Drainage | 9/19/2019 | | 9/27/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - Erosion and Sediment | 9/18/2019 | | 9/23/2019 | | PASS |
Andy J. Long
|
|
|
Main ESC permit is ESC19-00292 - to be issued with site development and grading permit GRD19-00067
|
Routing - MECHANICAL | 9/18/2019 | | 9/23/2019 | | FAIL |
Troy James
|
|
|
See eplan
|
Routing - PLANNING | 9/18/2019 | | 9/19/2019 | | FAIL |
Cody Riddle
|
|
|
The development agreement (CAR18-00021) required the developer explore sustainability measures (Section 5). A detailed summary of this effort, including specifics on what features are included, is required before issuance of building permits.
|
Routing - PUBLIC WORKS | 9/18/2019 | | 9/19/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Sewer Rating | 9/19/2019 | | 9/19/2019 | | PASS |
Morgan Webb
|
|
|
TRUNK AND TREATMENT WILL BE ASSESSED WITH FULL BUILD OUT. ASSESSMENT CHARGED WITH BLD19-02943
|
Routing PW Street Lights | 9/19/2019 | | 9/19/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 9/19/2019 | | 9/19/2019 | | PASS |
DeAnn Brown
|
|
|
Sewer connection approved under associated grading permit.
|
Routing PW Solid Waste | 9/19/2019 | | 9/19/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Addressing | 9/18/2019 | | 9/18/2019 | | FAIL |
Doug Chausow
|
|
|
Parcels must be consolidated before permit can be issued.
|
Routing - PLUMBING | 9/18/2019 | | 9/18/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 9/18/2019 | | PASS |
Julie Romig
|
|
|
|
Application received | | | 8/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 22 2019 1:16PM
|