BLD-Energy code compliance | 4/10/2020 | 4/10/2020 | 4/10/2020 | P | PASS |
Tell Riley
|
|
|
ok to cover, corrections made//walked framing with engineer, contractor, and I, corrections were made//
|
BLD-Wall cover | 4/10/2020 | 4/10/2020 | 4/10/2020 | A | FAIL |
Tell Riley
|
|
|
Tell, I am still in Montana but I had Joey take all the 6 inch lags and replace with 10 in lags Where needed. Carl Phone #: ###-#### Inspection requested via web by Carl Funkcn issued to remove gyp to see framing corrections and insulation//
|
BLD-Energy code compliance | 4/1/2020 | 4/2/2020 | 4/2/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk/need to see length of lags used in ledger areas, boxes onsite are 6" and some areas would require a 10" lag for the 3" minimum needed per plans//will check other corrections when re-schedule//
|
BLD-Framing/Rough-in | 3/29/2020 | 3/30/2020 | 3/30/2020 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk////see corrections prior to any cover approval//need letter from engineer//ok to insulate//
|
BLD-Framing/Rough-in | 3/26/2020 | 3/27/2020 | 3/27/2020 | A | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//used as conference with engineer of record and contractor//some engineering will need to be completed and corrections made in framing//need I joist manual for plumbing in Is//need truss engineering//
|
BLD-Framing/Rough-in | 3/25/2020 | 3/26/2020 | 3/26/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk
|
BLD-Wall Bracing | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk/nailing ok on firewall shear, per engineers email//
|
BLD-Wall Bracing | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | NR |
Tell Riley
|
|
|
carl - firewall nailing pattern Phone #: ###-####
|
Fees Due Hold | 3/5/2020 | | 3/6/2020 | | DONE |
Gabe Brenner
|
|
|
|
Routing - MECHANICAL | 3/4/2020 | | 3/4/2020 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Wall cover | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | PASS |
Mike Jordan
|
|
|
Firewall insulation Phone #: ###-#### Inspection requested via web by Carl Funk
|
BLD-Wall cover | 2/23/2020 | 2/24/2020 | 2/24/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//still needs Electrical approval for separation walls//
|
BLD-Wall cover | 2/20/2020 | 2/20/2020 | 2/20/2020 | A | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//still working on ELE// need to fix insulation//address fireblocking issue with Architect//remove siding in center unit to install 2 layers of 5/8 per detail//
|
Permit Ready to Issue | | | 2/19/2020 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/19/2020 | | DONE |
|
|
|
|
Plan assigned to (RDP) | 2/11/2020 | 2/11/2020 | 2/18/2020 | | DONE |
Rob Patrick
|
|
|
02/17 Plan Mod
|
Routing - PLAN CHECK | 2/18/2020 | | 2/18/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/18/2020 | | DONE |
Rob Patrick
|
|
|
|
Plan Modification Accepted | | | 2/11/2020 | | DONE |
|
|
|
2 copies of Sheet A4.4.
|
BLD-Wall cover | 2/5/2020 | 2/5/2020 | 2/5/2020 | A | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//CN posted//does not meet requirements for 2 hr assembly per plans//
|
BLD-Wall cover | 1/31/2020 | 2/3/2020 | 2/3/2020 | A | CANC |
Tell Riley
|
|
|
Phone #: ###-#### firewall Inspection requested via web by Carl Funk
|
BLD-Wall cover | 1/30/2020 | 1/31/2020 | 1/31/2020 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk/ needs plans
|
BLD-Wall Bracing | 1/30/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk,, exterior ok
|
BLD-Wall Bracing | 1/29/2020 | 1/29/2020 | 1/29/2020 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//still need hold downs nailed correctly//
|
BLD-Wall Bracing | 1/7/2020 | 1/8/2020 | 1/8/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk/CN issued//not quite ready//
|
BLD-Wall Bracing | 12/18/2019 | 12/19/2019 | 12/19/2019 | A | PART |
Tell Riley
|
|
|
Inspection requested via web by Carl Funk//Nailing and hardware ok in most locations--some strapping needs lowered//location near fire separation wall will need tied into shear wall, waiting for engineered detail//
|
BLD-Wall Bracing | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | CANC |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk
|
BLD-Wall Bracing | 12/16/2019 | 12/16/2019 | 12/16/2019 | A | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//used inspection as conference//
|
BLD-Foundation | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | PART |
Tell Riley
|
|
|
wip
|
BLD-Footing | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | PASS |
Tell Riley
|
|
|
SERGIO Phone #: ###-####//setbacks and rebar ok per plans//
|
OVERRIDE | | | 10/3/2019 | | |
|
|
|
|
Telephone call | | | 10/3/2019 | | DONE |
|
|
|
spoke with carl informing permit is ready and fee amount
|
Issue PAID IN FULL permit | | | 10/3/2019 | | DONE |
|
|
|
|
Plan assigned to (RDP) | 8/28/2019 | | 10/3/2019 | | DONE |
Rob Patrick
|
|
|
09/16 sfd L2 PAPER...Failed
|
Routing - PLAN CHECK | 10/3/2019 | | 10/3/2019 | | PASS |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 10/3/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/3/2019 | | DONE |
Rob Patrick
|
|
|
|
Inspection Record Card- Bld | | | 10/3/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/3/2019 | | DONE |
|
|
|
all 12 permits need issued at the same time
|
Plan resubmittals received | | | 10/2/2019 | | DONE |
|
|
|
Two copies each of structural design calcualtions stamped and taken to plan reviewer.
|
Plan resubmittals received | | | 9/27/2019 | | DONE |
|
|
|
Two copies of plan sheets A2.0, A2.2, A2.6, A2.7, A4.4, S2.0 and E2.1. taken to rob
|
1st review completed | | | 9/25/2019 | | FAIL |
Rob Patrick
|
|
|
Multiple Corrections
|
Routing - PLAN CHECK | 9/6/2019 | | 9/25/2019 | | FAIL |
Rob Patrick
|
|
|
Multiple Corrections
|
Routing - MECHANICAL | 8/28/2019 | | 9/6/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 9/5/2019 | | 9/5/2019 | | PASS |
Katelyn Menuge
|
|
|
Redlined facade and landscape changes.
|
Routing - PLANNING | 8/28/2019 | | 9/4/2019 | | PASS |
David Moser
|
|
|
|
Routing - PUBLIC WORKS | 8/28/2019 | | 9/3/2019 | | PASS |
Morgan Webb
|
|
|
CONTACT WEST BOISE SEWER DISTRICT ###-####
|
Routing - Addressing | 8/28/2019 | | 8/30/2019 | | PASS |
Doug Chausow
|
|
|
|
Route to Impact Fee Review | 8/28/2019 | 8/31/2019 | 8/29/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 8/28/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/28/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/28/2019 | | PASS |
|
|
|
|
Application received | | 8/22/2019 | | | |
|
|
|
|
Application received | | 8/22/2019 | | | |
|
|
|
|