Second Notice | | 5/17/2020 | 5/13/2020 | | DONE |
|
|
|
This permit finaled on the web by Ian Franklin
|
First Notice | | 4/13/2020 | 5/7/2020 | | DONE |
|
|
|
mailed 5-8-2020
|
Permanent Occupancy | | | 4/3/2020 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 4/2/2020 | 4/2/2020 | 4/2/2020 | | DONE |
Jason C. Taylor
|
|
|
No PW requirements for reconstructed building. JCT
|
BLD-Final | 3/31/2020 | 4/1/2020 | 4/1/2020 | P | PASS |
Mike Jordan
|
|
|
Please call 15 minutes before inspection for access to project. Late in the day if possible. Phone #: ###-#### Inspection requested via web by Ian Franklin
|
BLD-Final | 3/27/2020 | 3/27/2020 | 3/27/2020 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Final | 3/26/2020 | 3/27/2020 | 3/27/2020 | A | CANC |
Mike Jordan
|
|
|
Please call before arrival. Project is behind locked gates and no superintendent is on site. I am 15 minutes from the job site. Phone #: ###-#### Inspection requested via web by Ian Franklin. Moved to pm inspection.
|
FIRE-Final Inspection | 3/25/2020 | 3/26/2020 | 3/26/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Building numbers are installed, extinguishers mounted, and gate hardware exchanged. Review docs are on site with approved plans. Phone #: ###-#### Inspection requested via web by Ian Franklin
|
BLD-Final | 3/24/2020 | 3/25/2020 | 3/25/2020 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ian Franklin Inspection cancelled from web by: Ian Franklin
|
Zoning Approval | 3/25/2020 | 3/25/2020 | 3/25/2020 | | PASS |
Katelyn Menuge
|
|
|
|
FIRE-Final Inspection | 3/24/2020 | 3/24/2020 | 3/24/2020 | P | FAIL |
Troy Cobbley
|
|
|
Provide plans and small documents, provide fire extinguishers. May need single action hardware on the man gate as discussed.
Opticom has been tested by fire house #6 3/18/20 Phone #: ###-#### Inspection requested via web by Ian Franklin
|
BLD-Wall cover | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | PASS |
Mike Jordan
|
|
|
fire wall inspection Phone #: ###-#### Inspection requested via web by Glen Farrell
|
BLD-Framing/Rough-in | 2/11/2020 | 2/12/2020 | 2/12/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Glen Farrell
|
BLD-Wall cover | 1/23/2020 | 1/24/2020 | 1/24/2020 | A | PASS |
Mike Jordan
|
|
|
and insulation in the fire wall Phone #: ###-#### Inspection requested via web by Glen Farrell
|
BLD-Framing/Rough-in | 1/20/2020 | 1/21/2020 | 1/21/2020 | A | PASS |
Mike Jordan
|
|
|
can the inspector ring and hour before he goes there as i,am working on to jobs thanks Phone #: ###-#### Inspection requested via web by Glen Farrell
|
BLD-Footing | 12/19/2019 | 12/19/2019 | 12/19/2019 | P | PASS |
Mike Jordan
|
|
|
can they ring before they come Phone #: ###-#### Inspection requested via web by Glen Farrell
|
BLD-Footing | 12/17/2019 | 12/17/2019 | 12/17/2019 | P | CANC |
Mike Jordan
|
|
|
rebar Inspection Phone #: ###-#### Inspection requested via web by Glen Farrell
|
Issue PAID IN FULL permit | | | 12/5/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/5/2019 | | DONE |
|
|
|
|
Telephone call | | | 12/5/2019 | | DONE |
|
|
|
email permits to be sign to - reception@forgebuildings.com Eplan needs to be release
|
OVERRIDE | | | 12/4/2019 | | |
|
|
|
|
Plan assigned to (JG) | 9/18/2019 | 9/18/2019 | 12/4/2019 | | PASS |
Javier Guzman
|
|
|
11/29 3rd Rev, 502 Stor-IT Maple Grove, pend eng
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/4/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/4/2019 | | DONE |
|
|
|
MET JEFF@HATCHDA.COM
NEED
Revised Certificate of Value
GC FORM JEFF@HATCHDA.COM
ACHD
RP
|
Routing Off Site - STRUCTURAL | 11/25/2019 | | 12/4/2019 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by Stapley Engineering
|
Routing - PLAN CHECK | 11/25/2019 | | 12/3/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 11/25/2019 | | 11/25/2019 | | PASS |
Katelyn Menuge
|
|
|
Parapets okay.
|
Routing Off Site - STRUCTURAL | 11/12/2019 | | 11/21/2019 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by Stapley Engineering
|
Routing - PLAN CHECK | 11/12/2019 | | 11/19/2019 | | FAIL |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 10/30/2019 | 11/2/2019 | 10/31/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 9/17/2019 | 9/18/2019 | 10/30/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 10/30/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 9/18/2019 | | 10/24/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 9/18/2019 | | 10/16/2019 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by Stapley Engineering
|
Routing - MECHANICAL | 9/18/2019 | | 9/26/2019 | | PASS |
Troy James
|
|
|
No mechanical to review.
|
Routing PW Drainage | 9/18/2019 | | 9/20/2019 | | PASS |
Brian Murphy
|
|
|
BLD BURNED SAME FOUNDATION SAME SW SYSTEM EXISTING ONSITE
|
Routing PW Street Lights | 9/18/2019 | | 9/19/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 9/18/2019 | | 9/19/2019 | | PASS |
DeAnn Brown
|
|
|
No sewer facilities needed for new buildings.
|
Routing PW Solid Waste | 9/18/2019 | | 9/19/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Design Review | 9/18/2019 | | 9/18/2019 | | PASS |
Katelyn Menuge
|
|
|
DRH19-00308
|
Routing - PLUMBING | 9/18/2019 | | 9/18/2019 | | PASS |
Daryl Spivey
|
|
|
|
Routing - PLANNING | 9/18/2019 | | 9/18/2019 | | PASS |
Karla Nelson
|
|
|
|
Routing - Addressing | 9/18/2019 | | 9/18/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/18/2019 | | 9/18/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 9/18/2019 | | 9/18/2019 | | PASS |
Michael Zawacki
|
|
|
Waiver approved. Building is to bebuilt on footprint of old building that was demolished due to fire damage.
|
Intake Approval | | | 9/17/2019 | | PASS |
Michael Hanson
|
|
|
|
Intake Approval | | | 9/16/2019 | | FAIL |
Michael Hanson
|
|
|
Provide electrical COMcheck. (Didn't see it on SE-1)
Provide required clear stamping location in the bottom right of each sheet.
|
Intake Approval | | | 9/4/2019 | | FAIL |
Michael Hanson
|
|
|
Individually upload the FBC sheets.
Provide electrical COMcheck.
|
Application received | | | 8/27/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 27 2019 4:33PM
|