BLD-Energy code compliance | 6/3/2020 | 6/3/2020 | 6/3/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Gettman
|
BLD-Framing/Rough-in | 5/20/2020 | 5/20/2020 | 5/20/2020 | P | PASS |
Tony Young
|
|
|
Please call Gary 30 minutes prior to inspection and I wiI’ll meet you there. Thanks! Phone #: ###-#### Inspection requested via web by Gary Gettman
|
Routing - MECHANICAL | 3/2/2020 | | 3/2/2020 | | PASS |
Troy James
|
|
|
Submitted manual j report
|
BLD-Foundation | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PART |
Mike Jordan
|
|
|
They would like to pour this afternoon at 2:30. Early afternoon inspection if at all possible. Thanks. Phone #: ###-#### Inspection requested via web by Gary Gettman
|
BLD-Footing | 9/4/2019 | 9/4/2019 | 9/4/2019 | A | PASS |
Tony Young
|
|
|
Please call Gary at ###-#### prior to inspection and I will meet you there. Footings will be ready at 8:30. Thanks! Phone #: ###-#### Inspection requested via web by Gary Gettman
|
Routing Walk-In (Zoning) | 8/28/2019 | 8/28/2019 | 8/28/2019 | A | PASS |
Nicolette Womack
|
|
|
|
Routing Walk-In (BLD) | 8/28/2019 | 8/28/2019 | 8/28/2019 | A | DONE |
Rob Patrick
|
|
|
|
Plan assigned to (RDP) | 8/28/2019 | 8/28/2019 | 8/28/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/28/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 8/28/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/28/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/28/2019 | | 8/28/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 8/28/2019 | | DONE |
Rob Patrick
|
|
|
|
Inspection Record Card- Bld | | | 8/28/2019 | | DONE |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 8/28/2019 | | DONE |
Rob Patrick
|
|
|
|
Application received | | 8/28/2019 | | | |
|
|
|
|