BLD-Final | 4/10/2020 | 4/10/2020 | 4/10/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Rusty Cook
|
DOC - Permit Finaled | 4/10/2020 | 4/10/2020 | 4/10/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 2/5/2020 | 2/6/2020 | 2/6/2020 | A | PASS |
Jim Storey
|
|
|
Rusty Phone #: ###-####
|
BLD-Framing/Rough-in | 2/6/2020 | 2/6/2020 | 2/6/2020 | A | PASS |
Jim Storey
|
|
|
Rusty Phone #: ###-#### c/n made ok
|
BLD-Framing/Rough-in | 2/3/2020 | 2/3/2020 | 2/3/2020 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Rusty Cook f1 floor truss top chord cut at pan drain// ok to insulate.
|
BLD-Framing/Rough-in | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | PASS |
Jim Storey
|
|
|
We need soffit inspection for fire rated soffit. Phone #: ###-#### Inspection requested via web by Rusty Cook soffit ok
|
Routing - MECHANICAL | 1/24/2020 | | 1/24/2020 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Wall Bracing | 1/10/2020 | 1/10/2020 | 1/10/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Rusty Cook
|
BLD-Footing | 11/8/2019 | 11/8/2019 | 11/8/2019 | P | PART |
Jim Storey
|
|
|
pat Phone #: ###-#### wip verify p/l at wall insp.
|
BLD-Footing | 10/28/2019 | 10/29/2019 | 10/29/2019 | P | CANC |
Brandon Shaw
|
|
|
pat Phone #: ###-####
|
OVERRIDE | | | 9/26/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 9/5/2019 | 9/5/2019 | 9/26/2019 | | DONE |
Jenny Nelson
|
|
|
09/18 sfd L1 ePlan. 1st complete 9/19, specify mech equip
|
Issue PAID IN FULL permit | | | 9/26/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/26/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/26/2019 | | 9/26/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 9/26/2019 | | DONE |
|
|
|
|
1st review completed | | | 9/19/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 9/5/2019 | | 9/19/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 9/9/2019 | | 9/19/2019 | | PASS |
Jeff Lowe
|
|
|
comply with PUD18-00046
|
Route to Impact Fee Review | 9/5/2019 | 9/8/2019 | 9/6/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 9/5/2019 | | 9/6/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - MECHANICAL | 9/5/2019 | | 9/6/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PUBLIC WORKS | 9/5/2019 | | 9/5/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/5/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/5/2019 | | DONE |
|
|
|
|
Intake Approval | | | 9/5/2019 | | PASS |
|
|
|
|
Intake Approval | | | 8/29/2019 | | FAIL |
|
|
|
1. Need DR approval letter. 2. Fire-rated eave detail. 3. Stair section showing treads/risers at minimum (headroom and handrail is on notes in plan). 4. Crawl & Attic access. 5. Foundation vents or conditioned crawl details. 6. Acca (Man J) Report.
|
Application received | | | 8/28/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 28 2019 2:42PM
|