BLD-Final | 11/18/2019 | 11/18/2019 | 11/18/2019 | P | PASS |
Dave Hannah
|
|
|
Alex Phone #: ###-####
|
FIRE-Final Inspection | 11/13/2019 | 11/14/2019 | 11/14/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, sprinkler head has been adjusted and is code compliant, fire alarm inspection is complete, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection complete. Space was occupied before inspection process was completed.
ALEX Phone #: ###-####
|
FIRE-Final Inspection | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | FAIL |
Jim Page
|
|
|
Provide fire alarm notification in exam rooms as discussed, a seperate fire alarm permit will be required for fire alarm modificaitons. Sprinkler head in small storage room has sprinkler head closer than 4 inches too wall, relocate to be code compliant. Provide code compliant door hardware for pocket door as discussed.
|
BLD-Final | 10/14/2019 | 10/15/2019 | 10/15/2019 | A | NR |
Dave Hannah
|
|
|
Alex Phone #: ###-####
|
FIRE-Final Inspection | 10/14/2019 | 10/14/2019 | 10/14/2019 | P | CANC |
Jim Page
|
|
|
Called point of contact provided at 3:30PM and left a message, did not find area of work. Waited until 3:45PM for a call back but none was revieved, proceeded to next inspection, this request is cancelled and a new inspection request will need to be rescheduled.
Alex Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/11/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/11/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 8/31/2019 | 8/31/2019 | 9/10/2019 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 09/05 L1 IPM&R Exam Room Remodel ePlan
|
Routing - PLAN CHECK | 9/10/2019 | | 9/10/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/10/2019 | | DONE |
|
|
|
NEED
GC form
Revised Certificate of Value
|
Route to Impact Fee Review | 9/5/2019 | 9/8/2019 | 9/6/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLUMBING | 8/31/2019 | | 9/5/2019 | | PASS |
Dan Ediger
|
|
|
per plans and ISPC
|
1st review completed | | | 9/5/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 9/3/2019 | | 9/3/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/3/2019 | | 9/3/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - PLAN CHECK | 8/31/2019 | | 9/3/2019 | | FAIL |
Javier Guzman
|
|
|
|
Intake Approval | | | 8/30/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 8/28/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 28 2019 3:04PM
|