Case Summary (BLD) | | | 6/6/2020 | | DONE |
|
|
|
|
BLD-Final | 2/11/2020 | 2/11/2020 | 2/11/2020 | P | PASS |
Jim Storey
|
|
|
Please call ahead and I can meet onsite. Thanks Phone #: ###-#### Inspection requested via web by Alex McKinley
|
DOC - Permit Finaled | 2/11/2020 | 2/11/2020 | 2/11/2020 | P | PASS |
Jim Storey
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/13/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/6/2019 | 12/6/2019 | 12/12/2019 | | PASS |
Javier Guzman
|
|
|
12/17 plan mod Boise Bicycle Project - Solar ePlan
|
Routing - PLAN CHECK | 12/11/2019 | | 12/12/2019 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 12/12/2019 | | DONE |
|
|
|
plan mod approved
|
Routing - FIRE | 12/11/2019 | 12/11/2019 | 12/11/2019 | | PASS |
Mark Stumbaugh
|
|
|
plan mod Boise Bicycle Project - Solar ePlan
|
Plan Modification Accepted | | | 12/6/2019 | | DONE |
|
|
|
plan mod requested by Alex McKinley from Empowered Solar. As builts for solar panel. Sheet PV2
|
FIRE-Final Inspection | 11/27/2019 | 11/27/2019 | 11/27/2019 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection for scope of work complete, as-builts will be submitted showing solar panel reconfiguration, spacing requirements still met per building permit fire code review comments.
Can meet on site, please call with as much notice as possible. Thanks Phone #: ###-#### Inspection requested via web by Alex McKinley
|
Fees Due Hold | 10/15/2019 | | 11/27/2019 | | DONE |
Tiffany Carson-Herker
|
|
|
|
Telephone call | | | 10/21/2019 | | DONE |
|
|
|
GC sent signed permit but the fees have not been paid so i emailed the fees du to -alex@empowered.solar
it looks lijke Gemma had also contacted them before
|
Telephone call | | | 10/14/2019 | | DONE |
|
|
|
Called and emailed Alex that additional fees were erroneously not assesed when they paid for the permit $159.73 is due
|
Plan assigned to (JG) | 9/5/2019 | 9/5/2019 | 10/11/2019 | | PASS |
Javier Guzman
|
|
|
2nd rev, 09/24 (L3 - ePlan) BBP Solar Panels
|
Routing - PLAN CHECK | 10/8/2019 | | 10/11/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/11/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/11/2019 | | DONE |
|
|
|
Need GC
|
Issue PAID IN FULL permit | | | 10/11/2019 | | DONE |
|
|
|
emailed the permit to be signed and sent back to alex@empowered.solar as well as the rec of payment and asked him in the email to send back to permits@cityofbboise.org
|
Routing - FIRE | 10/8/2019 | 10/8/2019 | 10/10/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Route to Impact Fee Review | 9/27/2019 | 9/30/2019 | 10/1/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 9/5/2019 | 9/5/2019 | 9/26/2019 | | FAIL |
Mark Stumbaugh
|
|
|
10/02-BBP Solar Panels 520
|
1st review completed | | | 9/26/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 9/5/2019 | | 9/20/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 9/5/2019 | | 9/11/2019 | | PASS |
Josh Wilson
|
|
|
|
Intake Approval | | | 9/4/2019 | | PASS |
Javier Guzman
|
|
|
Prescreen approved by JG.
|
Intake Approval | | | 8/30/2019 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following for prescreen:
• Provide Design Review/Planning Zoning approval documents.
• Provide structural calculations stamped, signed and dated by an Idaho licensed engineer showing that the existing roof structure can support the additional gravity/dead load weight of the ballasted solar panels system. If new solar ballasted system increases the design gravity load more than 5% structurally, provide engineered plans and calculations for new elements that will strengthen, supplement, or replace existing load-carrying members as needed.
|
Telephone call | | | 8/30/2019 | | DONE |
|
|
|
Received revised certificate of value from applicant to include total value of project (including value of donated materials). Fee will be based on Boise City PV Policy.
|
Application received | | | 8/29/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 29 2019 1:07PM
|