BLD-Aging Inspection | 4/2/2020 | 4/2/2020 | 4/2/2020 | | DEFR |
Brandon Shaw
|
|
|
|
Extend Permit 90/180 days | 4/2/2020 | 4/2/2020 | 4/2/2020 | P | DONE |
Brandon Shaw
|
|
|
|
Place hold on job | 11/22/2019 | | 11/29/2019 | | DONE |
Judith Amador
|
|
|
MET- Need signed permit
|
Telephone call | | | 11/26/2019 | | DONE |
|
|
|
called Webster Construction and spoke with Dave and inform him that we needed the sign permit to be returned.
|
BLD-Framing/Rough-in | 11/19/2019 | 11/19/2019 | 11/19/2019 | P | PASS |
Brandon Shaw
|
|
|
Please call ahead, need access to all units - David Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/15/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/15/2019 | | DONE |
|
|
|
|
Telephone call | | | 11/15/2019 | | DONE |
|
|
|
email sent for permit to be sign to-webster.construction@yahoo.com Eplan needs to be release
|
Plan assigned to (M_H) | 8/31/2019 | | 9/5/2019 | | DONE |
Michael Hanson
|
|
|
09/05 L1 River Run window replace ePlan
|
Routing - PLAN CHECK | 8/31/2019 | | 9/5/2019 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 9/5/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/5/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 9/5/2019 | | DONE |
|
|
|
MET VROSS.WEBSTERCONSTRUCTION@GMAIL.COM
NEED
GC FORM
|
Intake Approval | | | 8/30/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 8/29/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 29 2019 1:38PM
|