BLD-Final | 4/15/2020 | 4/15/2020 | 4/15/2020 | P | PASS |
Mike Jordan
|
|
|
*screened* Call for access code - Jeff Phone #: ###-####
|
DOC - Permit Finaled | 4/15/2020 | 4/15/2020 | 4/15/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 4/15/2020 | 4/15/2020 | 4/15/2020 | P | DONE |
Mike Jordan
|
|
|
4.6
|
BLD-Energy code compliance | 12/24/2019 | 12/26/2019 | 12/26/2019 | P | PASS |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/24/2019 | 12/26/2019 | 12/26/2019 | P | PASS |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
BLD-Energy code compliance | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | FAIL |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | FAIL |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Complete lateral bracing on A06 truss. (missed bracing on last A06 truss) Needs to encapsulate insulation on all six sides at perimeter of vaulted ceiling. do not cover.
|
BLD-Framing/Rough-in | 12/19/2019 | 12/19/2019 | 12/19/2019 | P | FAIL |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Complete lateral bracing on A03,A04,A05 and A06 trusses. Fireblock concealed space by shower/tub at ceiling. Provide strongbacks on both gable ends. provide 2x6 studs under top plate breaks in garage, both sides, (east and west)
|
BLD-Wall Bracing | 11/21/2019 | 11/21/2019 | 11/21/2019 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Footing | 11/4/2019 | 11/4/2019 | 11/4/2019 | P | PASS |
Mike Jordan
|
|
|
pouring at 1:45 // James Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/17/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/17/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/16/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 9/3/2019 | 9/3/2019 | 9/16/2019 | | DONE |
Jenny Nelson
|
|
|
09/16 sfd L1 ePlan
|
Routing - PLAN CHECK | 9/3/2019 | | 9/16/2019 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 9/16/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/16/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 9/16/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/3/2019 | 9/6/2019 | 9/4/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 9/3/2019 | | 9/3/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/3/2019 | | 9/3/2019 | | PASS |
Ethan Mansfield
|
|
|
|
Routing - Addressing | 9/3/2019 | | 9/3/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/3/2019 | | 9/3/2019 | | PASS |
Morgan Webb
|
|
|
|
Telephone call | | | 9/3/2019 | | DONE |
|
|
|
Called Cathy to verify the sq ft on the plans. On the floor plan is shows 1220 and 1120. Cathy stated the correct sq ft is 1120 sq ft.
Cathy informed me that there was a shed on the property and not a home. No record of demo of shed.
|
Plans ACCEPTED BY PLAN TECH | | | 9/3/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/3/2019 | | DONE |
|
|
|
|
Intake Approval | | | 9/3/2019 | | PASS |
|
|
|
|
Application received | | | 8/30/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 30 2019 2:52PM
|