BLD-Final | 2/25/2020 | 2/25/2020 | 2/25/2020 | P | PASS |
Mike Jordan
|
|
|
sTANLEY Phone #: ###-####
|
DOC - Permit Finaled | 2/25/2020 | 2/25/2020 | 2/25/2020 | P | PASS |
Mike Jordan
|
|
|
All issues have been resolved.
|
BLD-Final | 2/24/2020 | 2/24/2020 | 2/24/2020 | P | NR |
Mike Jordan
|
|
|
Stanley Phone #: ###-####. Provide exterior landings on detached structures. Provide smoke detectors and CO detector in existing house.
|
BLD-Energy code compliance | 12/23/2019 | 12/24/2019 | 12/24/2019 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Wall cover | 12/19/2019 | 12/20/2019 | 12/20/2019 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. Shower stall and kitchenet has been removed. Drains have been plugged in wall and below in crawl space. Water supply lines also removed.
|
BLD-Energy code compliance | 12/19/2019 | 12/20/2019 | 12/20/2019 | A | PASS |
Mike Jordan
|
|
|
music room - John Phone #: ###-####
|
BLD-Energy code compliance | 12/16/2019 | 12/16/2019 | 12/16/2019 | P | PART |
Mike Jordan
|
|
|
John Phone #: ###-####. Addition and shop only. No music room at this time.
|
Meeting | | | 12/12/2019 | | DONE |
|
|
|
Parcel Owner came in to talk about ADU app, hooking his property up to sewer, and/or having temporary occupancy while waiting for the sewer/ADU process.
|
BLD-Framing/Rough-in | 12/10/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. Addition and detached shop only ok to insulate at this time. Detached music room has a shower and that at this time is not allowed. Also plumbing for a seperate sink has been installed that is not shown on approved plans.
|
BLD-Wall Bracing | 10/25/2019 | 10/28/2019 | 10/28/2019 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. Addition and south detached structure ok.
|
OVERRIDE | | | 10/25/2019 | | |
|
|
|
|
Routing Walk-In (BLD) | 10/25/2019 | 10/25/2019 | 10/25/2019 | P | DONE |
Josh Bogle
|
|
|
consult with Josh on a chagne that has been done to the approval plans
|
Plan assigned to (JAB) Josh | 10/25/2019 | 10/25/2019 | 10/25/2019 | | PASS |
Josh Bogle
|
|
|
plan mod on storage room
|
Routing - PLAN CHECK | 10/25/2019 | | 10/25/2019 | | PASS |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 10/25/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 10/25/2019 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 10/25/2019 | | DONE |
|
|
|
submitting change on storage room
|
CHANGE STATUS TO (ISS) | | | 10/25/2019 | | DONE |
|
|
|
plan mod
|
BLD-Wall Bracing | 10/23/2019 | 10/24/2019 | 10/24/2019 | A | PART |
Mike Jordan
|
|
|
jon Phone #: ###-####- please call for access. Add more blocking and holdown to home addition. Detached structure on north side ok to tyvek. South detached structure will need to resubmit for openeingings in exterior wall .
|
BLD-Conference | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | DONE |
Mike Jordan
|
|
|
possible kitchen being places in either 500sqft detached office or 500sqft detached shop. Will verify on next inspection.
|
BLD-Foundation | 9/16/2019 | 9/16/2019 | 9/16/2019 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Footing | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | PASS |
Brandon Shaw
|
|
|
John Phone #: ###-####
|
BLD-Footing | 9/10/2019 | 9/11/2019 | 9/11/2019 | P | FAIL |
Tell Riley
|
|
|
john Phone #: ###-####//no plans available onsite//told worker onsite to call inspection in for tomorrow///
|
OVERRIDE | | | 9/4/2019 | | |
|
|
|
|
Routing Walk-In (BLD) | 9/4/2019 | 9/4/2019 | 9/4/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 9/4/2019 | | 9/4/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 9/4/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 9/4/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 9/4/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/4/2019 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 9/3/2019 | 9/3/2019 | 9/3/2019 | A | PASS |
Ethan Mansfield
|
|
|
No shower allowed in music room w/o ADU permit.
|
Routing Walk-In (BLD) | 9/3/2019 | 9/3/2019 | 9/3/2019 | A | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 9/3/2019 | | 9/3/2019 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 9/3/2019 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 9/3/2019 | | | |
|
|
|
|