BLD-Aging Inspection | 7/28/2020 | 7/28/2020 | 7/28/2020 | | DEFR |
Brandon Shaw
|
|
|
|
Extend Permit 90/180 days | 7/28/2020 | 7/28/2020 | 7/28/2020 | P | DONE |
Brandon Shaw
|
|
|
|
BLD-Final | 3/16/2020 | 3/16/2020 | 3/16/2020 | P | FAIL |
Brandon Shaw
|
|
|
Smoke alarms to be as per R314...
|
BLD-Framing/Rough-in | 1/28/2020 | 1/29/2020 | 1/29/2020 | A | PASS |
Brandon Shaw
|
|
|
Correction SAT... OK to cover...
|
BLD-Other | 1/27/2020 | 1/28/2020 | 1/28/2020 | A | PART |
Dave Hannah
|
|
|
Vicky- to inspect the header Phone #: ###-#### up stairs closit ok but header over window is under sized calls for 9 1/2 x 3 1/2 lvl and two tremers each end
|
BLD-Framing/Rough-in | 9/25/2019 | 9/26/2019 | 9/26/2019 | A | PART |
Brandon Shaw
|
|
|
Phase i of III... Removal of fireplace insert, frame out duct chace... Phase II- enlarge window opening, and Phase III- closet in up stairs bedroom, to at later dates...
|
BLD-Other | 9/26/2019 | 9/26/2019 | 9/26/2019 | A | CANC |
Brandon Shaw
|
|
|
Soffit
|
Plan assigned to (JAR) | 9/3/2019 | 9/5/2019 | 9/10/2019 | | DONE |
Julie Romig
|
|
|
09/10 - L2 Waterside Condos Briggs Residence
|
Routing - PLAN CHECK | 9/5/2019 | | 9/10/2019 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 9/10/2019 | | DONE |
Julie Romig
|
|
|
|
Case Summary (BLD) | | | 9/10/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/10/2019 | | DONE |
|
|
|
please have owner add the verbiage that they are part of the Living Trust then re scan
|
Inspection Record Card- Bld | | | 9/10/2019 | | DONE |
|
|
|
|
Telephone call | | | 9/10/2019 | | DONE |
|
|
|
called Vicki Briggs to let know permit is ready buit we need the GC form to reflect that she is part of the living trust that owns the parcel. also what the fee amount is-left message on her phone ###-####
|
Issue PAID IN FULL permit | | | 9/10/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/10/2019 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/4/2019 | | DONE |
|
|
|
|
Intake Approval | | | 9/4/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/4/2019 | | DONE |
|
|
|
|
Application received | | 9/3/2019 | | | |
|
|
|
|