BLD-Energy code compliance | 5/3/2020 | 5/4/2020 | 5/4/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by John Cloninger//insulation ok per notes on plans//
|
BLD-Framing/Rough-in | 3/26/2020 | 3/26/2020 | 3/26/2020 | A | PASS |
Tell Riley
|
|
|
Prints are on the wall next to the window inside the structure. Plumbing inspection sticker is on the window. All mechanical and electrical will be surface mounted and inspected after the inside surface is covered. Phone #: ###-#### Inspection requested via web by John Cloninger//RFI provided//shear ok//framing ok//ok to insulate//
|
BLD-Framing/Rough-in | 3/24/2020 | 3/25/2020 | 3/25/2020 | A | NR |
Tell Riley
|
|
|
Complete wall bracing inspection - The hold downs are replaced with epoxy set studs. Inspect building so we can place insulation Phone #: ###-#### Inspection requested via web by John Cloninger/need trades inspections, truss engineering, approved plans onsite//
|
BLD-Wall Bracing | 3/24/2020 | 3/25/2020 | 3/25/2020 | A | PEND |
Tell Riley
|
|
|
Complete wall bracing inspection - The hold downs are replaced with epoxy set studs Phone #: ###-#### Inspection requested via web by John Cloninger//need engineers approval for alternate locations of hold downs//
|
BLD-Wall Bracing | 2/20/2020 | 2/21/2020 | 2/21/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by John Cloninger//need to nails with 8d nails per plans//provide engineers approval of wedge type anchors for hold downs in place of cast in place anchors//block all edges//will call for shear nailing//
|
BLD-Wall Bracing | 2/19/2020 | 2/20/2020 | 2/20/2020 | P | CANC |
Tell Riley
|
|
|
Shear inspection for the building Phone #: ###-#### >> Inspection requested via web by John Cloninger Inspection cancelled from web by: John Cloninger
|
BLD-Concrete | 1/27/2020 | 1/30/2020 | 1/30/2020 | A | PASS |
Jim Storey
|
|
|
MTI is scheduled to inspect the rebar at 9:30 am followed by a 3 cy pour at 10 am. This pour is for the small SOG inside the building. Phone #: ###-#### Inspection requested via web by John Cloninger si on site pending reports.
|
BLD-Foundation | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | DEFR |
Tell Riley
|
|
|
Footer inspection Phone #: ###-#### Inspection requested via web by John Cloninger//defer to specials//
|
BLD-Foundation | 1/21/2020 | 1/21/2020 | 1/21/2020 | A | PART |
Tell Riley
|
|
|
We are pouring the two short return walls and the building face of the utility trench in the future building. Nothing too structural. The pour is scheduled for 11 am with MTI and and RSCI quality control both present. Phone #: ###-#### Inspection requested via web by John Cloninger//rebar clearances ok//Sill plate anchors preset in wall on exterior side//ok pending all specials//
|
BLD-Concrete | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | PART |
Tell Riley
|
|
|
Rusinr Phone #: ###-####//specials onsite//ok to pour when temps meet engineers specs--heaters onsite//pendinng specials//
|
BLD-Footing | 1/10/2020 | 1/13/2020 | 1/13/2020 | A | DEFR |
Tell Riley
|
|
|
rebar- rues Phone #: ###-####//defer to specials, they will be onsite for rebar, formwork and concrete//
|
BLD-Footing | 1/8/2020 | 1/8/2020 | 1/8/2020 | P | PART |
Tell Riley
|
|
|
I (John Cloninger) will be out of town. Rusmir Civic will be the onsite contact - his number is listed above. The 10 am pour will include the east wall and the north wall. If weather permits the slab on grade for the tank bases will also be poured. If there is any trouble my number is ###-####. Phone #: ###-#### Inspection requested via web by John Cloninger//prior footing inspection ok pending specials on 12/30/2019//today wall and slab ok pending specials on rebar, forms, and concrete specials//
|
(F) Reprint permit | | | 12/24/2019 | | DONE |
|
|
|
|
Telephone call | | | 12/24/2019 | | DONE |
|
|
|
emailed the permit to be signed to trent@rscigroup.com, NEED to save it to Documents
|
Issue PAID IN FULL permit | | | 12/18/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/18/2019 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/17/2019 | 11/27/2019 | 12/17/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 11/20/19 (New Building - 25 days) (eplan - 59 sheets) PWE-849 Chemical Storage (routed to staff)
|
Routing Off Site - STRUCTURAL | 12/11/2019 | | 12/17/2019 | | PASS |
Carl Westfall
|
|
|
Chris Holladay (AHJ)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/17/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/17/2019 | | DONE |
|
|
|
ALL MET- Need
ACHD
GC Form
|
Route to Impact Fee Review | 12/10/2019 | 12/13/2019 | 12/12/2019 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals received | | | 12/11/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/11/2019 | | 12/11/2019 | | PASS |
Carl Westfall
|
|
|
pending structural
|
1st review completed | | | 12/10/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 12/10/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/23/2019 | | 12/10/2019 | | PASS |
Carl Westfall
|
|
|
Pending structural
|
Routing - FIRE | 10/17/2019 | 10/23/2019 | 12/9/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 10/23/2019 | | 11/4/2019 | | FAIL |
Carl Westfall
|
|
|
Chris Holladay (AHJ)
|
Routing PW Flood Plain | 10/23/2019 | | 10/29/2019 | | CANC |
Jason C. Taylor
|
|
|
Project is outside Special Flood Hazard Area, no floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
Routing PW Drainage | 10/23/2019 | | 10/29/2019 | | CANC |
Jason C. Taylor
|
|
|
No review required. JCT
|
Routing PW Sewer Design | 10/23/2019 | | 10/29/2019 | | PASS |
DeAnn Brown
|
|
|
Building drain connects to existing plant drain manhole/pipeline.
|
Routing - Erosion and Sediment | 10/23/2019 | | 10/28/2019 | | PASS |
Michael Zawacki
|
|
|
Please refer to ESC19-01503 for site.
|
Routing PW Environmental | 10/23/2019 | | 10/28/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 10/23/2019 | | 10/24/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Street Lights | 10/23/2019 | | 10/24/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - Addressing | 10/23/2019 | | 10/24/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/23/2019 | | 10/23/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 10/23/2019 | | 10/23/2019 | | PASS |
Karla Nelson
|
|
|
|
Intake Approval | | | 10/17/2019 | | PASS |
Michael Hanson
|
|
|
|
Intake Approval | | | 10/11/2019 | | FAIL |
Michael Hanson
|
|
|
10/11
Construction drawings must be stamped, signed, and dated by an Idaho licensed engineer.
-------------------------------
Provide required #502 checklist and required documentation indicated in the checklist.
|
Intake Approval | | | 9/18/2019 | | FAIL |
Michael Hanson
|
|
|
Provide required #502 checklist and required documentation indicated in the checklist.
|
Application received | | | 9/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 4 2019 1:41PM
|