BLD-Final | 6/4/2020 | 6/5/2020 | 6/5/2020 | A | PASS |
Jim Storey
|
|
|
Please call for garage code B4 Phone #: ###-#### Inspection requested via web by Mick Davis
|
DOC - Permit Finaled | 6/5/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 5/6/2020 | 5/6/2020 | 5/6/2020 | | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 12/23/2019 | 12/24/2019 | 12/24/2019 | A | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Framing/Rough-in | 12/17/2019 | 12/17/2019 | 12/17/2019 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Mick Davis need header at ducts 2nd floor continous bearing gable at house garage . ok to insulate. mech aproved jack
|
BLD-Conference | 12/13/2019 | 12/16/2019 | 12/16/2019 | P | PASS |
Jim Storey
|
|
|
Review plans in Referance to WUI. Please call or text prior to heading to job site. Thank You Mick Davis Phone #: ###-#### Inspection requested via web by Mick Davis class a rooffing the only requirment.
|
Routing - MECHANICAL | 12/13/2019 | | 12/13/2019 | | PASS |
Troy James
|
|
|
New manual j report.
|
BLD-Wall Bracing | 12/3/2019 | 12/3/2019 | 12/3/2019 | P | PASS |
Jim Storey
|
|
|
Lanz Phone #: ###-####
|
Inspection Record Card- Bld | | | 11/25/2019 | | DONE |
|
|
|
|
BLD-Foundation | 10/10/2019 | 10/11/2019 | 10/11/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Foundation | 10/10/2019 | 10/11/2019 | 10/10/2019 | P | CANC |
Jim Storey
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru Inspection cancelled via mobile web on Thursday, October 10, 2019.
|
BLD-Footing | 10/9/2019 | 10/10/2019 | 10/10/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Footing | 10/8/2019 | 10/9/2019 | 10/9/2019 | P | DEFR |
Jim Storey
|
|
|
As late as possible Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru// out of time.
|
Inspection Record Card- Bld | | | 9/30/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/30/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/24/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 9/11/2019 | 9/11/2019 | 9/24/2019 | | DONE |
Jenny Nelson
|
|
|
09/24 sfd L1 ePlan
|
Routing - PLAN CHECK | 9/11/2019 | | 9/24/2019 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 9/24/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 9/24/2019 | | DONE |
|
|
|
NEED-MET
RP
|
Routing - MECHANICAL | 9/11/2019 | | 9/18/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 9/11/2019 | 9/14/2019 | 9/12/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 9/11/2019 | | 9/11/2019 | | PASS |
Sue Cummings
|
|
|
see minor redline
|
Routing - Addressing | 9/11/2019 | | 9/11/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/11/2019 | | 9/11/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/11/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/11/2019 | | DONE |
|
|
|
|
Intake Approval | | | 9/11/2019 | | PASS |
|
|
|
|
Intake Approval | | | 9/6/2019 | | FAIL |
|
|
|
NEED
MANUAL (HVAC)
ATTIC/CRAWL SPACE
STAIR DETAILS (WIDTH, HANDRAIL, TREAD, RISERS & HEADROOM)
ELECTRICAL (STAIR LIGHTING, S.D. & C.M.)
BATH EXHAUST FANS
|
Intake Approval | | | 9/5/2019 | | FAIL |
|
|
|
**PRESCREEN NOT COMPLETED** Must upload drawings as individual sheets
|
Application received | | | 9/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 4 2019 2:12PM
|