Change Expiration Date Only | | | 5/27/2020 | | DONE |
Jason Blais
|
|
|
A 180 day extension is approved for an issued permit. This is the first extension request.
|
BLD-Aging Inspection | 4/16/2020 | 4/16/2020 | 4/20/2020 | | PEND |
Tell Riley
|
|
|
|
BLD-Aging Inspection | 4/15/2020 | 4/15/2020 | 4/16/2020 | | PEND |
Tell Riley
|
|
|
no inspections requested since December
|
BLD-Wall Bracing | 12/3/2019 | 12/3/2019 | 12/3/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by greg bauer
|
BLD-Wall Bracing | 12/2/2019 | 12/2/2019 | 12/2/2019 | P | FAIL |
Tell Riley
|
|
|
Greg Phone #: ###-####//add blocking and nails shear locations at plate per plan detail//add HDU 2 and install per manufacturers installation instructions//framing cannot be passed until trades rough ins complete and inspected//
|
BLD-Framing/Rough-in | 12/2/2019 | 12/2/2019 | 12/2/2019 | P | CANC |
Tell Riley
|
|
|
Greg Phone #: ###-####//no trades complete//needs shear inspection//will schedule for shear//
|
Plan assigned to (J_N) | 11/25/2019 | 11/25/2019 | 12/2/2019 | | DONE |
Jenny Nelson
|
|
|
plan mod: structural changes to framing
|
Routing - PLAN CHECK | 12/2/2019 | | 12/2/2019 | | PASS |
Jenny Nelson
|
|
|
Plan modification - structural engineering updated
|
Permit Ready to Issue | | | 12/2/2019 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
CHANGE STATUS TO (ISS) | | | 12/2/2019 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 11/23/2019 | 11/25/2019 | 11/25/2019 | A | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by greg bauer//need to submit for plan mod for change at front entry and shear changes from engineer//
|
Plan Modification Accepted | | | 11/25/2019 | | DONE |
|
|
|
plan mod
|
BLD-Framing/Rough-in | 11/11/2019 | 11/12/2019 | 11/12/2019 | A | FAIL |
Tell Riley
|
|
|
Rough framing/Sheer wall inspection to allow us to cover with house wrap. Phone #: ###-#### Inspection requested via web by greg bauer//no plans onsite///please have plans located onsite for all inspections//
|
BLD-Wall Bracing | 11/4/2019 | 11/5/2019 | 11/5/2019 | P | DONE |
Tell Riley
|
|
|
Do you need to see the installation of threaded anchor bolts drilled and epoxy into existing concrete wall for residential project? I know for commercial you have see this being done Phone #: ###-#### Inspection requested via web by greg bauer//answered questiosn//
|
BLD-Footing | 10/6/2019 | 10/7/2019 | 10/7/2019 | A | PASS |
Tell Riley
|
|
|
Post Footing and west basement wall extension. Phone #: ###-#### Inspection requested via web by greg bauer//post footing ok per plans//
|
Routing Walk-In (BLD) | 9/6/2019 | 9/6/2019 | 9/6/2019 | A | FAIL |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Jenny Nelson
|
|
|
|
Inspection Record Card- Bld | | | 9/6/2019 | | DONE |
Jenny Nelson
|
|
|
|
Case Summary (BLD) | | | 9/6/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/6/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 9/6/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/6/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/6/2019 | | 9/6/2019 | | FAIL |
Josh Bogle
|
|
|
plans incomplete
|
1st review completed | | | 9/6/2019 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 9/6/2019 | | | |
|
|
|
|