BLD-Final | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.96
|
BLD-Final | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kyle Seick Inspection cancelled from web by: Kyle Seick
|
PubWorks Occupancy Approval | 4/17/2020 | 4/17/2020 | 4/17/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Photos of the landscaping and a video of the drainage connection has been received by Public Works Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Other | 1/13/2020 | 1/14/2020 | 1/14/2020 | A | PASS |
Brandon Shaw
|
|
|
Soffit. Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Energy code compliance | 1/10/2020 | 1/10/2020 | 1/10/2020 | P | PEND |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 1/9/2020 | 1/9/2020 | 1/9/2020 | P | FAIL |
Brandon Shaw
|
|
|
See pgs S1.1 & S2 for details and plan notes- red marks- for corrections... A35 clips Trimmer studs Column and king studs... OK to insulate...
|
BLD-Framing/Rough-in | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | NR |
Brandon Shaw
|
|
|
Need mech ruogh-in... Provide truss Engineering...
|
BLD-Wall Bracing | 12/17/2019 | 12/17/2019 | 12/17/2019 | P | PART |
Brandon Shaw
|
|
|
1st floor only... Work in progress...
|
BLD-Foundation | 10/22/2019 | 10/22/2019 | 10/22/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progres...
|
BLD-Footing | 10/21/2019 | 10/21/2019 | 10/21/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 10/17/2019 | 10/17/2019 | 10/17/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 10/10/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/10/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/26/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 9/11/2019 | 9/11/2019 | 9/26/2019 | | DONE |
Jenny Nelson
|
|
|
09/30 sfd L2 ePlan
|
Routing - PLAN CHECK | 9/11/2019 | | 9/26/2019 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 9/26/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 9/26/2019 | | DONE |
|
|
|
met
|
Routing - MECHANICAL | 9/11/2019 | | 9/17/2019 | | PASS |
Troy James
|
|
|
|
Routing PW Grading-Hillside | 9/11/2019 | | 9/16/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - FIRE | 9/11/2019 | 9/11/2019 | 9/13/2019 | | PASS |
Lee G Meredith
|
|
|
09/24-5916 Hootowl Residential 404 LGM
Fire Sprinklers not required
|
Route to Impact Fee Review | 9/11/2019 | 9/14/2019 | 9/12/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 9/11/2019 | | 9/12/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/11/2019 | | 9/11/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 9/11/2019 | | 9/11/2019 | | PASS |
Michael Zawacki
|
|
|
|
Routing - PLANNING | 9/11/2019 | | 9/11/2019 | | PASS |
Sue Cummings
|
|
|
|
Intake Approval | | | 9/11/2019 | | PASS |
|
|
|
prescreen pass
|
Plans ACCEPTED BY PLAN TECH | | | 9/11/2019 | | DONE |
|
|
|
|
Intake Approval | | | 9/11/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/11/2019 | | DONE |
|
|
|
|
Application received | | | 9/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 9 2019 7:41AM
|