First Notice | | 5/11/2020 | 7/9/2020 | | DONE |
|
|
|
mailed 7-9-2020
|
Print Occupancy Form | | | 5/1/2020 | | DONE |
|
|
|
|
Permanent Occupancy | | | 5/1/2020 | | DONE |
|
|
|
|
BLD-Final | 4/27/2020 | 4/28/2020 | 4/28/2020 | P | PASS |
Tell Riley
|
|
|
Call prior to going Phone #: 2088413111 >> Inspection requested via mobile web by Marcus Tam//corrections made, paper and soap dispenser lowered, signage added//final complete per scope//no signature card onsite//
|
BLD-Card not on site to sign | 4/14/2020 | 4/15/2020 | 4/15/2020 | P | CANC |
Tell Riley
|
|
|
Call prior to going Phone #: 2088413111 >> Inspection requested via mobile web by Marcus Tam
|
BLD-Final | 4/14/2020 | 4/15/2020 | 4/15/2020 | P | FAIL |
Tell Riley
|
|
|
Phone #: 2088413111 >> Inspection requested via mobile web by Marcus Tam//need to post correct unit space of 200//add signage to restrooms//dispensers for paper towels, etc are to high, see plans for correct heights//
|
FIRE-Final Inspection | 4/14/2020 | 4/15/2020 | 4/15/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: 2088413111 >> Inspection requested via mobile web by Marcus Tam
|
BLD-Final | 3/17/2020 | 3/18/2020 | 3/18/2020 | A | NR |
Tell Riley
|
|
|
Marcus Phone #: ###-####//need fire life safety passed prior to final//
|
FIRE-Final Inspection | 3/17/2020 | 3/18/2020 | 3/18/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need previous items corrected and new plans/mods on site.
Marcus Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 3/17/2020 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 2/18/2020 | 2/18/2020 | 2/21/2020 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 2/20/2020 | | 2/21/2020 | | PASS |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 2/21/2020 | | DONE |
|
|
|
PLAN MOD
|
Plan Modification Accepted | | | 2/18/2020 | | DONE |
|
|
|
modified the scope of work on the cover sheet and modified the amount of exit signs
|
BLD-Final | 2/11/2020 | 2/12/2020 | 2/12/2020 | P | NR |
Tell Riley
|
|
|
Marcus Phone #: ###-####///needs fire life safety final complete prior to final building inspection//
|
FIRE-Final Inspection | 2/11/2020 | 2/12/2020 | 2/12/2020 | A | FAIL |
Troy Cobbley
|
|
|
See the list of correction marked in red on the floor plan which include providing the exit signs and emergency lights as per plans, providing single action hardware on one of the main exit doors, mount the fire extinguisher, remove the temp wall, provide plan modifications for the wall that was not constructed.
Marcus Phone #: ###-####
|
Plan Reviewer's activity | | | 2/6/2020 | | DONE |
Brian McGowan
|
|
|
Uploaded revised Certificate of Value to Tidemark and ePlan
|
Plan Reviewer's activity | | | 1/30/2020 | | DONE |
Brian McGowan
|
|
|
Spoke with Marcus Tam about removing the electrical inspection from the Scope of work. He has an electrical value stated which would nmean he is doing electrical work and would need an inspection. He is going to resubmit (email me) a Certificate of Value without an Electrical Value.
Added Plan Reviewer Activity to state no electrical was done and no inspection required. Spoke with Tell to let him know and he will verfiy during his inspection.
|
BLD-Final | 1/24/2020 | 1/27/2020 | 1/27/2020 | P | NR |
Tell Riley
|
|
|
marcus Phone #: ###-####//needs fire life safety//had a phone conference to discuss other inspections noted,, advised to have electrical and mechanical removed from permit//
|
Plan Reviewer's activity | | | 1/22/2020 | | DONE |
Brian McGowan
|
|
|
Returned Tam's phone call, could not leave a message.
|
Inspection Record Card- Bld | | | 12/5/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/5/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/5/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/24/2019 | | DONE |
|
|
|
MET
Need GC
Need Rev Val
|
Plan assigned to (BJM) | 9/11/2019 | 9/11/2019 | 10/23/2019 | | DONE |
Brian McGowan
|
|
|
10/29- 1st Review Complete- North Cole Office Suites ePlan
|
Routing - PLAN CHECK | 10/23/2019 | | 10/23/2019 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2019 | | DONE |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 10/18/2019 | 10/21/2019 | 10/21/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 9/11/2019 | | 10/18/2019 | | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 10/18/2019 | | DONE |
Brian McGowan
|
|
|
|
Routing - Addressing | 9/11/2019 | | 9/11/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/11/2019 | | 9/11/2019 | | PASS |
Morgan Webb
|
|
|
NO NEW FIXTURES. WEST BOISE SEWER DISTRICT
|
Intake Approval | | | 9/10/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 9/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 9 2019 8:47AM
|