BLD-Final | 3/2/2020 | 3/3/2020 | 3/3/2020 | P | PEND |
Mike Jordan
|
|
|
Loyd- call 30 min prior Phone #: ###-####. Needs to provide electrical permit for equipment in shop.
|
BLD-Final | 2/19/2020 | 2/20/2020 | 2/21/2020 | P | CANC |
Mike Jordan
|
|
|
Loyd- call for access Phone #: ###-####
|
FIRE-Final Inspection | 2/19/2020 | 2/20/2020 | 2/20/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Exterior exit hardware to be corrected prior to a building inspection as discussed.
Loyd- call for access Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/15/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/15/2020 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/14/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 1/14/2020 | | DONE |
|
|
|
NEED
GC
Revised Certificate of Value
|
Plan assigned to (M_H) | 9/16/2019 | | 1/14/2020 | | DONE |
Michael Hanson
|
|
|
1st review completed - 10/10 #520 L3 ePlan - Koenig Knives
|
Routing - FIRE | 1/13/2020 | 1/13/2020 | 1/13/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Route to Impact Fee Review | 10/10/2019 | 10/13/2019 | 10/11/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 9/16/2019 | | 10/10/2019 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 10/10/2019 | | FAIL |
Michael Hanson
|
|
|
|
Routing - FIRE | 9/16/2019 | 9/16/2019 | 10/7/2019 | | FAIL |
Mark Stumbaugh
|
|
|
10/10 (520) Koenig Knives, ePlan
|
Routing - PLANNING | 9/16/2019 | | 9/18/2019 | | PASS |
Karla Nelson
|
|
|
All interior work, no planning approval needed.
|
Routing - Addressing | 9/16/2019 | | 9/16/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/16/2019 | | 9/16/2019 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 9/13/2019 | | PASS |
|
|
|
|
Application received | | | 9/11/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 11 2019 9:45AM
|