BLD-Final | 11/8/2019 | 11/12/2019 | 11/12/2019 | P | PASS |
Dave Hannah
|
|
|
Elena Phone #: ###-####
|
FIRE-Final Inspection | 11/8/2019 | 11/12/2019 | 11/12/2019 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, hood suppression system inspection is current with no modifications, fire exitnguishers are placed with current inspection tags. Final life fire safety inspection complete, signature provided on signature card.
Elena Phone #: ###-####
|
Permanent Occupancy | | | 11/12/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/2/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/2/2019 | | DONE |
|
|
|
pleae let customer know they need a plumbing permit and a MIS inspection for the mechanical
|
Telephone call | | | 10/2/2019 | | DONE |
|
|
|
called Elena to let knpw permit is ready
|
Print Occupancy Form | | | 10/2/2019 | | DONE |
|
|
|
|
Meeting | | | 10/2/2019 | | DONE |
|
|
|
Elena came in to pick up her permit and showed me a new floor plan with different equipement and sink location. After speaking with Carl M., I let her know that this would be a resubmittal and would require further review. She said she would come back to speak with Julie. I gave her back her updated plans as she told me she intended ot speak to Julie about them after 2pm today.
|
Plan Reviewer's activity | | | 10/2/2019 | | DONE |
Julie Romig
|
|
|
Applicant had a revised plan to use different kitchen appliances under the hood. Appliances are to fit under the hood with 6" cleraance on each side and are to comply with the 2012 IMC. New plan approved by building and mechanical and added to the permit set.
|
Print Occupancy Form | | | 10/2/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/2/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 9/11/2019 | 9/17/2019 | 10/1/2019 | | DONE |
Julie Romig
|
|
|
10/02 - 2nd Rev - 1st Rev Comp - 528 Alyonka Russion Cuisine
|
Routing - MECHANICAL | 10/1/2019 | | 10/1/2019 | | PASS |
Troy James
|
|
|
See note on floor plan
|
Routing - PLAN CHECK | 10/1/2019 | | 10/1/2019 | | PASS |
Julie Romig
|
|
|
|
Case Summary (BLD) | | | 10/1/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/11/2019 | | 9/23/2019 | | PASS |
Julie Romig
|
|
|
9/23/19 Gave applicant the mechanical write up.
|
Routing - PUBLIC WORKS | 9/17/2019 | | 9/23/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 9/17/2019 | | 9/23/2019 | | FAIL |
Troy James
|
|
|
See plan review report attached.
|
1st review completed | | | 9/23/2019 | | DONE |
Julie Romig
|
|
|
|
Routing PW Environmental | 9/18/2019 | | 9/20/2019 | | PASS |
Rick Christenson
|
|
|
Exsiting 1000 Gallon Grease Interceptor.
|
Intake Approval | | | 9/17/2019 | | PASS |
|
|
|
Application received 09/11/19 pending confirmation from applicant regarding floor plan. On 09/17/19, applicant confirmed that they would be installing a reach-in refrigerator instead of a walk-in cooler. Plans routed on 09/17/19 after confirmation received.
|
First Notice | | 11/22/2019 | | | |
|
|
|
|
Application received | | 9/11/2019 | | | |
|
|
|
|