Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-03563
StatusFinaled
Name KC GARDNER RIVERWOODS LC
Site Address 800 W MAIN ST Unit: 1100
Project NameA10 Capital - Suite 1100
Customer NumberVANILLA T.I. BLD19-03680
ePlanReviewYes
Description
(A10 CAPITAL - 11TH FLOOR) (2 permits in ePlan Under BLD19-03563) Permit to split a full floor tenant into two separate tenant spaces. A10 CAPITAL (current tenant) will occupy Suite 1100 and the remainder will be a vanilla tenant and be Suite 1150. Work to include: minor demolition, construction of non-load bearing interior walls, doors, and minor electrical. Approval is contingent on adhering to the approved plans, local codes and ordinances. Interior finishes shall be in compliance with Ch. 8 of the 2015 IBC. This building is fully fire sprinkled because it is a high rise building. Any alterations or modifications to the buildings fire sprinkler or fire alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise fire department. MDH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Meeting  2/28/2020 DONE
larren emailed in final value
First Notice 1/20/20202/7/2020 DONE
mailed 2-10-20
BLD-Final1/9/20201/10/20201/10/2020APASS
DetailsDave Hannah
laren novak Phone #: ###-####
Permanent Occupancy  1/10/2020 DONE
FIRE-Final Inspection1/8/20201/9/20201/9/2020PPASS
DetailsJim Page
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.

Laren Phone #: ###-####
BLD-Conference12/19/201912/19/201912/19/2019PDONE
DetailsDave Hannah
Laren Phone #: ###-####
BLD-Framing/Rough-in11/4/201911/5/201911/5/2019PPASS
DetailsDave Hannah
Larren Phone #: ###-####
Issue PAID IN FULL permit  10/22/2019 DONE
Print Occupancy Form  10/22/2019 DONE
Plan assigned to (M_H)9/18/2019 10/17/2019 DONE
DetailsMichael Hanson
1st review completed - 09/27 #518 L2 ePlan - A10 - Suite 1100
Routing - PLAN CHECK10/17/2019 10/17/2019 PASS
DetailsMichael Hanson
PLANS/APPL TAKEN TO FRONT DESK  10/17/2019 DONE
DetailsMichael Hanson
Permit Ready to Issue  10/17/2019 DONE
Need GC
Need Rev Val
Route to Impact Fee Review9/26/20199/29/20199/26/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - PLAN CHECK9/18/2019 9/26/2019 FAIL
DetailsMichael Hanson
See changemarks in ePlan for corrections required. MDH
1st review completed  9/26/2019 DONE
DetailsMichael Hanson
Routing - Addressing9/18/2019 9/24/2019 PASS
DetailsDoug Chausow
Suite 1100
Routing - PUBLIC WORKS9/18/2019 9/19/2019 PASS
DetailsMorgan Webb
NO NEW PLUMBING
Intake Approval  9/16/2019 PASS
DetailsJavier Guzman
Application received  9/11/2019 DONE
Application submitted via PDS Online on Sep 11 2019 1:09PM