First Notice | | 6/25/2020 | 7/9/2020 | | DONE |
|
|
|
mailed 7-9-2020
|
Permanent Occupancy | | | 6/15/2020 | | DONE |
|
|
|
|
BLD-Final | 6/9/2020 | 6/9/2020 | 6/9/2020 | P | PASS |
Dave Hannah
|
|
|
Bruce Phone #: ###-####
|
BLD-Final | 6/4/2020 | 6/4/2020 | 6/5/2020 | P | PEND |
Dave Hannah
|
|
|
Bruce *screened* Phone #: ###-#### ok for tco but needs to install glass in doors
|
FIRE-Final Inspection | 6/2/2020 | 6/4/2020 | 6/4/2020 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extingiushers are placed with current inspection tags. Final life fire safety inspection is complete, signatures provided on permit sign off card.
Bruce *screeend* Phone #: ###-####
|
FIRE-Final Inspection | 6/1/2020 | 6/3/2020 | 6/2/2020 | A | CANC |
Jim Page
|
|
|
Rescheduled for 04JUN2020 to coincide with fire alarm inspection, this request is cancelled.
Bruce *screeend* Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 5/28/2020 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/28/2020 | 4/28/2020 | 5/8/2020 | | PASS |
Carl Westfall
|
|
|
plan mod - St. Luke's offices (plan intake approved)
|
Routing - PLAN CHECK | 5/7/2020 | | 5/8/2020 | | PASS |
Carl Westfall
|
|
|
IBC plan mod review approved
|
Plan Reviewer's activity | | | 5/8/2020 | | PASS |
|
|
|
Plan mod review approved
|
Permit Ready to Issue | | | 5/8/2020 | | DONE |
|
|
|
plan mod approved
|
Routing - PLAN CHECK | 5/4/2020 | | 5/7/2020 | | PASS |
Carl Westfall
|
|
|
Plan intake review approved the 2nd time because problems with ePlanReview deleted what had been done previously.
|
Routing - PLAN CHECK | 5/7/2020 | | 5/7/2020 | | PASS |
Carl Westfall
|
|
|
Plan mod review approved
|
Plan Modification Accepted | | | 5/4/2020 | | DONE |
|
|
|
Workflow in ePlanReview received
|
Plan Modification Accepted | | | 4/28/2020 | | DONE |
|
|
|
removal of conference rooms in N.W. corner and replace w/additional cubicle space.
Electrical revisions included all associated changes related to removal of conference rooms, along with miscellaneous changes to power and data requested by owner.
Mechanical revision include all associated changes related to removal of conference rooms, along with miscellaneous changes requested by owner.
|
BLD-Ceiling Grid Inspection | 3/24/2020 | 3/25/2020 | 3/26/2020 | P | PASS |
Dave Hannah
|
|
|
Bruce Phone #: ###-####
|
BLD-Framing/Rough-in | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | PART |
Dave Hannah
|
|
|
Bruce- Phone #: ###-#### hard lids in rest rooms ok to cover
|
BLD-Framing/Rough-in | 2/14/2020 | 2/18/2020 | 2/18/2020 | A | PASS |
Dave Hannah
|
|
|
bruce Phone #: ###-#### ok to cover restrooms
|
BLD-Framing/Rough-in | 2/11/2020 | 2/12/2020 | 2/12/2020 | A | NR |
Dave Hannah
|
|
|
Bruce Phone #: ###-####
|
BLD-Framing/Rough-in | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | PART |
Jim Storey
|
|
|
Bruce Phone #: ###-####// small offices out of the core area ok to start gyp.// c/n for ft backing/ fire stopping floor 2hr plm and ele.// patch 2 hr fireprooffing.
|
Print Occupancy Form | | | 12/2/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/2/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/21/2019 | | DONE |
|
|
|
MET
NEED
GC
Revised Certificate of Value
|
Plan assigned to (CJW) | 9/30/2019 | 10/25/2019 | 11/20/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 10/18/19 (L-3 - 15 days) (eplan - 60 sheets) St. Luke’s Integrated Health Technologies Office (back to applicant)
|
Routing - PLAN CHECK | 11/19/2019 | | 11/20/2019 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/15/2019 | | 11/19/2019 | | FAIL |
Carl Westfall
|
|
|
Mec and Plum drawings did not provide the required stamp space.
|
Plan resubmittals received | | | 11/19/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/15/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 10/24/2019 | 10/27/2019 | 10/25/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 9/30/2019 | 9/30/2019 | 10/24/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 10/24/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/24/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/30/2019 | | 10/24/2019 | | FAIL |
Carl Westfall
|
|
|
|
Routing - PLUMBING | 9/30/2019 | | 10/7/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 9/30/2019 | | 10/4/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/30/2019 | | 10/1/2019 | | PASS |
David Moser
|
|
|
office remodel of 4th floor and allowed in C-1 zone
|
Routing - Addressing | 9/30/2019 | | 10/1/2019 | | PASS |
Doug Chausow
|
|
|
4th Floor, Suite 400
|
Routing - PUBLIC WORKS | 9/30/2019 | | 10/1/2019 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 9/30/2019 | | PASS |
|
|
|
|
Intake Approval | | | 9/19/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• Plan sheet ID1.2B, A3.1B, A4.3B, A7.0B, A7.1B, A9.1B required to be stamped by an Idaho licensed architect.
• Per ePlan submittal standards the reserve the bottom right corner on all the drawing plumbing and mechanical plan sheets for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block. see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
• Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block on plan sheet E13.0 see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
|
Application received | | | 9/13/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 13 2019 1:54PM
|