BLD-Final | 9/25/2019 | 9/26/2019 | 9/26/2019 | A | CANC |
Tony Young
|
|
|
Scott Phone #: ###-####
|
FIRE-Final Inspection | 9/25/2019 | 9/25/2019 | 9/25/2019 | P | FAIL |
Jim Page
|
|
|
Provide fire extinguisher as stated on city approved drawings. Provide sprinkler escutcheon in restroom, escutcheon is missing. Remove thumb-turn deadbolt on rear exit door, door hardware must comply with the 2015 Intenational fire code, section 1010.1.9.1.
ins Scott Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/23/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/20/2019 | | DONE |
|
|
|
|
Telephone call | | | 9/20/2019 | | DONE |
|
|
|
customer called. told him that he needs to come in and pick up the permit
|
Print Occupancy Form | | | 9/20/2019 | | DONE |
|
|
|
|
Telephone call | | | 9/20/2019 | | |
|
|
|
Called to leave a message, but the name on the VM was not the applicant. Emailed the applicant to let them know that their permit is ready.
|
Routing - PLAN CHECK | 9/16/2019 | | 9/19/2019 | | PASS |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 9/18/2019 | | 9/19/2019 | | DONE |
Michael Hanson
|
|
|
09/20 #528 L2 Paper - HEMP WORLD Occ Eval
|
1st review completed | | | 9/19/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2019 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 9/19/2019 | | DONE |
Michael Hanson
|
|
|
|
Plan assigned to (JG) | 9/16/2019 | | 9/18/2019 | | DEFR |
Javier Guzman
|
|
|
09/20 L2 (HEMP WORLD) Occ Eval paper
|
Routing - PUBLIC WORKS | 9/16/2019 | | 9/18/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 9/16/2019 | | 9/17/2019 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/16/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/16/2019 | | DONE |
|
|
|
|
Intake Approval | | | 9/16/2019 | | PASS |
|
|
|
|
Application received | | 9/16/2019 | | | |
|
|
|
|