Permanent Occupancy | | | 10/18/2019 | | DONE |
|
|
|
|
BLD-Final | 10/2/2019 | 10/3/2019 | 10/3/2019 | P | PASS |
Tell Riley
|
|
|
around 12:15//re- inspect for occupancy//door locks changed//no other changes//final complete//
|
BLD-Final | 9/30/2019 | 10/2/2019 | 10/2/2019 | A | NR |
Tell Riley
|
|
|
Joan Phone #: ###-####//single action door handle will be installed tomorrow//will reshedule for PM//
|
FIRE-Final Inspection | 9/30/2019 | 10/1/2019 | 10/1/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. The door to corridor to be provided with single action hardware as discussed prior to a building inspection.. Joan Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/30/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/17/2019 | | 9/24/2019 | | PASS |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 9/20/2019 | | 9/24/2019 | | DONE |
Michael Hanson
|
|
|
09/24 #528 L2 Paper - Transformational Healthcare
|
1st review completed | | | 9/24/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2019 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 9/24/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 9/24/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/24/2019 | | DONE |
|
|
|
|
Telephone call | | | 9/24/2019 | | DONE |
|
|
|
spoke with joan informing her this permit is ready
|
Plan assigned to (JAR) | 9/17/2019 | 9/17/2019 | 9/20/2019 | | DEFR |
Julie Romig
|
|
|
09/24 - 528 Transformational Healthcare
|
Routing - Addressing | 9/17/2019 | | 9/19/2019 | | PASS |
Doug Chausow
|
|
|
Correct Suite is #125
|
Routing - PUBLIC WORKS | 9/19/2019 | | 9/19/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/17/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/17/2019 | | DONE |
|
|
|
occupancy fee taken
|
Intake Approval | | | 9/17/2019 | | PASS |
|
|
|
|
First Notice | | 10/28/2019 | | | |
|
|
|
|
Application received | | 9/17/2019 | | | |
|
|
|
|