Permit Information
Permit NumberBLD19-03667
StatusFinaled
Name CM COMPANY
Site Address 720 E PARK BLVD Unit: 110
Project NameSLCP Break Room Remodel
Customer Number 
ePlanReviewYes
Description
(SLMC - MSTI - 1ST FLOOR SUITE 110 BREAK ROOM T.I.) This is a scope of work permit a certificate of completion shall be issued upon completion. Permit to remodel an existing 100 sqft. break room. Work to include: demo existing door and section of non-load bearing interior wall, new sink, microwave countertop and cased opening, minor mechanical work, plumbing work, and electrical work. Approval is contingent on adhering to the approved plans, local codes and ordinances. Interior finishes shall be in compliance with Ch. 8 of the 2015 IBC. This building is fully fire sprinkled. Any alterations or modifications to the buildings fire sprinkler or fire alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise fire department. MDH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Plan Reviewer's activity  4/9/2020 DONE
DetailsMichael Hanson
Revised mechanical work value and removed the inspection requirement for mechanical.
Letter of compliance/Occupancy  4/9/2020 DONE
DOC - Permit Finaled  4/9/2020 DONE
per BLD-Final inspection that passed 3/31/20 by 425
BLD-Final3/31/20203/31/20203/31/2020PPASS
DetailsDave Hannah
bruce Phone #: ###-####
FIRE-Final Inspection3/23/20203/24/20203/24/2020APASS
DetailsJim Page
Final life fire safety inspection for area of work is complete.

bruce Phone #: ###-####
BLD-Ceiling Grid Inspection3/20/20203/23/20203/23/2020APASS
DetailsDave Hannah
Bruce Phone #: ###-####
Issue PAID IN FULL permit  1/9/2020 DONE
Inspection Record Card- Bld  1/9/2020 DONE
Plan assigned to (M_H)10/1/2019 10/10/2019 DONE
DetailsMichael Hanson
1st review completed - 10/04 #518 L1 ePlan - SLCP Break Room Remodel
Routing - PLAN CHECK10/10/2019 10/10/2019 PASS
DetailsMichael Hanson
PLANS/APPL TAKEN TO FRONT DESK  10/10/2019 DONE
DetailsMichael Hanson
Permit Ready to Issue  10/10/2019 DONE
all met: seans@cmcompany.com

NEED
GC
Revised Certificate of Value
Route to Impact Fee Review10/4/201910/7/201910/7/2019 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - Addressing10/1/2019 10/4/2019 PASS
DetailsMichael Hanson
Per ePlan approval.
1st review completed  10/4/2019 DONE
DetailsMichael Hanson
Routing - PLAN CHECK10/1/2019 10/4/2019 FAIL
DetailsMichael Hanson
See changemarks in ePlan for corrections required.
Routing - PUBLIC WORKS10/1/2019 10/1/2019 PASS
DetailsMorgan Webb
No new plumbing. Credit for demo
Intake Approval  10/1/2019 PASS
DetailsJavier Guzman
Application received  9/17/2019 DONE
Application submitted via PDS Online on Sep 17 2019 1:59PM